1035. To ask the Minister for Education and Skills the status of the provision of a permanent site for a school (details supplied); and if she will make a statement on the matter. [30422/22]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
The acquisition of the site for the school referred to by the Deputy was completed in 2020.
The building project for the school is being delivered under my Department's Design and Build programme. This delivery programme uses a professional external Project Manager to progress the project through the relevant stages of architectural planning, tender and construction.
The Letter of Acceptance issued to the successful Contractor on 18thMay 2022 commencing the school building contract and the contractor has mobilised on site.