Written answers

Tuesday, 31 May 2022

Department of Transport, Tourism and Sport

Rail Network

Photo of Mark WardMark Ward (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

116. To ask the Minister for Transport, Tourism and Sport when Kishogue train station will open to the public; the cost of this; the reason for the delay; and if he will make a statement on the matter. [27289/22]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

As the Deputy may be aware, the National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area including, in consultation with Iarnród Éireann (IÉ), Kishogue station. 

I am informed by the NTA that extensive work is needed by IÉ before Kishogue Station can be brought into use, including meeting present day accessibility and systems requirements which are above and beyond the original requirements. 

The investment will total circa €3.8 million and it is anticipated that the station will become operational for the public in 2023.