512. To ask the Minister for Education and Skills the date construction will start on a project (details supplied). [23140/22]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The Letter of Intent (LOI) issued on 15th February 2022 to the preferred tenderer.  This allows the preferred bidder to put in place the Bond, Insurances and confirmations of all legal arrangements required under the Contract.  

Following receipt of all the necessary documentation, the Department will be in a position to issue the Letter of Acceptance (LOA), which will allow the contractor to mobilise on site.  

My Department will advise the Board of Management when the Letter of Acceptance issues and advise of the start date of the construction.

Photo of Seán SherlockSeán Sherlock (Cork East, Labour)
Link to this: Individually | In context | Oireachtas source

513. To ask the Minister for Education and Skills the date construction will start on a project (details supplied). [23141/22]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The Letter of Intent (LOI) issued on 15th February 2022 to the preferred tenderer. This allows the preferred bidder to put in place the Bond, Insurances and confirmations of all legal arrangements required under the Contract.

Following receipt of all the necessary documentation, the Department will be in a position to issue the Letter of Acceptance (LOA), which will allow the contractor to mobilise on site.

My Department will advise the Board of Management when the Letter of Acceptance issues and advise of the start date of the construction.

Photo of Emer HigginsEmer Higgins (Dublin Mid West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

514. To ask the Minister for Education and Skills the timeline for the delivery of the new school building for a school (details supplied); and if she will make a statement on the matter. [23171/22]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The school building project referred to by the Deputy is being delivered under my Department's Design & Build Programme and planning permission for the project has been received.

My Department is currently considering the timeline for the progression to tender of a number of Design & Build projects, including the permanent accommodation for the school referred to and will advise the school's patron body further as soon as possible.

Pending delivery of the permanent building project, my Department will continue to address the interim accommodation needs of the school in conjunction with Dublin & Dún Laoghaire ETB.