489. To ask the Minister for Education and Skills her views on the expansion to a double stream school for a national school (details supplied) in County Wicklow. [4854/22]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I can confirm to the Deputy, that My Department received a request for a change of status from the school in question from a single stream fully vertical, co-educational school to a two stream, fully vertical co-educational school from September 2022. 

As part of the assessment process, my Department has taken into account the demographic projections and current capacity for the Greystones school planning area.  These projections indicate that there is already significant additional capacity available and that an increase from a one stream to a two stream status for the school in question is not warranted. In addition to other schools, the school planning area includes a new 24 classroom multi denominational primary school with substantial current capacity for additional enrolments. 

The application from the school in question was assessed by my Department in this context and the school have been notified of the decision.

Photo of Richard Boyd BarrettRichard Boyd Barrett (Dún Laoghaire, People Before Profit Alliance)
Link to this: Individually | In context | Oireachtas source

490. To ask the Minister for Education and Skills if she will provide a report on the online patronage process system that was opened in 2018 to decide 42 new schools to include name of school and catchment area, type of patronage of each school; if enrolment has opened on the schools; if the schools have temporary sites or permanent sites or both identified; the stage the building of these schools is at; when they are expected to be completed; and if she will make a statement on the matter. [4855/22]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I wish to advise the Deputy that the information requested relating to the 42 new schools, announced in 2018, is set out in tabular format for ease of reference.  

When a new school is being established to cater for demographic need a patronage process is run. This patronage process is open to all patron bodies and prospective patrons. Parental preferences for each patron, from parents of children who reside in the school planning areas concerned, together with the extent of diversity currently available in these areas, are key to decisions in relation to the outcome of this process.

The Online Patronage Process System (OPPS) has been developed by the Department to provide objective information to all parents and guardians which will allow them to make an informed choice in expressing a preference for their preferred model of patronage for their child’s education.

The patronage process for new schools is overseen by an external independent advisory group, the New Schools Establishment Group (NSEG). Following their consideration of the Department’s assessment reports, the NSEG will submit a report with recommendations to the Minister for consideration and final decision. The assessment reports and the NSEG recommendations for all such patronage processes are available on the Department's website (www.education.ie) and gov.ie.

All school building projects are progressed through the preliminary and detailed design stages aligning to my Department's Design Team Procedures prior to proceeding to tender and construction. These stages ensure that all projects are designed against the twin benchmarks of quality and cost control. Under these procedures my Department engages with the Project Manger to ensure that high standards in respect of both benchmarks are met. My Department constantly endeavours to progress projects through the stages of architectural planning, tender and construction in the shortest timeframes possible consistent with ensuring high quality and cost effective design.

As with all school building projects, pre planning meetings are required with the Local Authority in advance of preparing a Planning Application. This is to ensure the highest probability of a successful planning application in the shortest time possible. A considerable amount of work is required following the pre-planning meeting to prepare a suitably detailed application. The Department must await a decision on planning from the local authority. A notification to grant planning can be received after 8 weeks, although there is a possibility for the Local Authority to request further information (RFI). There is always also the possibility of an An Bord Pleanala Appeal (ABP) and if this occurs it may add a further six to eight months or more to the final planning decision date.  If planning is delayed, the Department has to put contingency arrangements in place to support the operation of schools.  

It is not therefore, possible to provide an indicative timeframe for the progression of projects to tender, construction and completion stages until such time as the necessary statutory approvals have been secured.

Post Primary

- Announced 
for 
School Planning Area  School Name  Roll Number establishment  Established  Patron  Permanent Site Status Building Project
Donaghmede_Howth_D13/Belmayne/Clongriffin  Belmayne ETSS  68346T 2019 2019 Educate Together  Acquired Stage 3
GalwayCity & Oranmore (Regional Solution)  Galway ETSS  68347V 2019 2019 Educate Together  Negotiations Site Acquisition Process
Laytown & Drogheda (Regional Solution)  Drogheda ETSS  68348A 2019 2019 Educate Together  Agreement in principle  Stage 1
Wicklow  Wicklow ETSS  68345R 2019 2019 Educate Together  Negotiations Site Acquisition Process
Blanchardstown_West D15 & BlanchardstownVge_D15 (Regional Solution)  Ériu Community College  76574F 2020 2020 Dublin and Dún Laoghaire Education and Training Board (DDLETB)  Negotiations Site Acquisition Process
Goatstown_Stillorgan DLR  Goatstown Educate Together Secondary School 68366C 2020 2020 Educate Together  Acquired Stage 2a
Enfield (Kilcock school planning area)  Enfield Community College  76595N 2020 2020 Louth and Meath Education and Training Board (LMETB)  Acquired Stage 2b
Citywest/Saggart (Tallaght & Newcastle_Rathcoole school planning areas) (Regional Solution)  Coláiste Pobail Fóla  76594L 2020 2020 Dublin and Dún Laoghaire Education and Training Board (DDLETB)  ETB Property Stage 2b
Dublin6_Clonskeagh & Dublin_6W (Regional Solution)  Harold’s Cross Educate Together Secondary School  68365A 2020 2020 Educate Together  Acquired Stage 2b
Ballincollig  Le Cheile Secondary School Ballincollig  68385G 2021 2021 Le Chéile Schools Trust  Negotiations Site Acquisition Process
Booterstown_Blackrock & Dunlaoghaire (Regional Solution)  Booterstown Blackrock and Dunlaoghaire Educate Together Secondary School  68387K 2021 2021 Educate Together  Acquired Stage 2b
Donaghmede_Howth_D13/Baldoyle/Stapolin  Patron to confirm  N/A 2021 Deferred  TBD  Negotiations Site Acquisition Process
Dublin2_Dublin4  Patron to confirm  N/A 2021 Deferred  TBD  Acquired Project Brief
Kilcoole & Greystones (Regional Solution)  Greystones Community College  76596P 2021 2020 Kildare and Wicklow Education and Training Board (KWETB)  Agreement in principle  Stage 1
Sallynoggin_Killiney_DLR/Cherrywood  Patron to confirm  N/A 2021 Deferred  TBD  Acquired Stage 2b
Drumcondra_Marino_Dublin1  Patron to confirm  N/A 2022 Deferred  TBD  Negotiations Project Brief

Building Project

Site Acquisition - site may be acquired by the Department or by the school's patron

Project Brief stage - this includes determining the project brief and schedule of accommodation

Stage 1 - Preliminary

Stage 2 - Design (which is divided into Stage 2a - Developed Sketch Scheme and Stage 2b - Detailed Design)

Stage 3 - Tender Action, Evaluation and Award

Stage 4 - Construction

* Pre-designated as an Irish-medium school

Primary

No.  School Planning Area  School Name  Roll Number Announced  for establishment  Established  Patron  Permanent Site Status Building Project
1 Booterstown_Blackrock  Gaelscóil Laighean  20518E 2019 2019 An Foras Pátrúnachta  Agreement in principle with Local Authority executive, subject to approval by Elected Members  Site Acquisition Process
2 Donaghmede_Howth_D13  Stapolin ETNS  20519G 2019 2019 Educate Together  Acquired Stage 3
3 Drumcondra_Marino_Dublin1  Gaelscóil Áine  20517C 2019 2019 An Foras Pátrúnachta  Negotiations Site Acquisition Process
4 Dublin6_Clonskeagh & Dublin_6W (Regional Solution)  Harolds Cross ETNS  20520O 2019 2019 Educate Together  Acquired Stage 2b
5 Dunshaughlin  Dunshaughlin Community National School  20521Q 2019 2020 Louth & Meath Education & Training Board  Acquired Stage 2b
6 Glasheen_CorkCity/Pouladuff  South Lee ETNS  20522S 2019 2019 Educate Together  Agreement in principle with Local Authority executive, subject to approval by Elected Members  Site Acquisition Process
7 Goatstown_Stillorgan_DLR  Goatstown Stillorgan ETNS  20523U 2019 2019 Educate Together  Acquired Stage 2a
8 Kilcoole/Newtownmountkennedy  Newtownmountkennedy ETNS  20524W 2019 2019 Educate Together  Acquired Stage 1
9 Killester_Raheny_Clontarf  KRC ETNS  20525B 2019 2019 Educate Together  Negotiations Site Acquisition Process
10 Leixlip  Leixlip ETNS  20526D 2019 2019 Educate Together  Negotiations Site Acquisition Process
11 Maynooth  Gaelscóil Ruairí  20527F 2019 2019 An Foras Pátrúnachta  ETB Property Stage 2b
12 Swords/South  Rivervalley Community National School  20528H 2019 2019 Dublin & Dun Laoghaire ETB  Negotiations Site Acquisition Process
13 Swords/North  Broadmeadow CNS  20529J 2019 2020 Dublin & Dun Laoghaire ETB  Minister Property Pre Stage 1
14 Carrigaline  Owenabue Educate Together National School  20534C 2020 2020 Educate Together  Negotiations Project Brief
15 Donabate  Gaelscoil na Mara*  20530R 2020 2020 An Foras Pátrúnachta  Approval in Principle Site Acquisition Process
16 Newcastle_Rathcoole/Saggart  Rathcoole Educate Together National School  20549P 2020 2020 Educate Together  ETB Property Stage 2a
17 Sallynoggin_Killiney_DLR/Cherrywood  Cherrywood Educate Together National School  20535E 2020 2020 Educate Together  Acquired Stage 4 (expected completion July 2022)
18 Bray/Woodbrook Shanganagh  Patron to confirm  20536G 2021 Deferred  TBD  Negotiations Site Acquisition Process
19 Clondalkin_D22  Patron to confirm  20537I 2021 Deferred  TBD  Minister Property Project Brief
20 Donaghmede_Howth_D13  Gaelscoil Ghráinne Mhaol*  20538K 2021 2021 An Forus Patrunachta  Minister Property Stage 1
21 Dublin2_Dublin4  Gaelscoil Eoin*  20539M 2021 2021 An Forus Patrunachta  Minister Leased Property Stage 1
22 Gurranbraher_CorkCity  Patron to confirm  20540U 2021 Deferred  TBD  Agreement in principle  Site Acquisition Process
23 Kilkenny/City, Western Environs  Patron to confirm  20541W 2021 Deferred  TBD  Aquired Site Acquisition Process
24 Naas  Patron to confirm  20542B 2021 Deferred  TBD  Negotiations Site Acquisition Process
25 Sallynoggin_Killiney_DLR/North  Sallynoggin ETNS  20543D 2021 Deferred  Educate Together  Agreement in principle  Stage 1
26
Sallynoggin_Killiney_DLR/Cherrywood  Patron to confirm*  20544F 2022 Deferred  TBD  Negotiations Site Acquisition Process

Building Project

Site Acquisition - site may be acquired by the Department or by the school's patron

Project Brief stage - this includes determining the project brief and schedule of accommodation

Stage 1 - Preliminary

Stage 2 - Design (which is divided into Stage 2a - Developed Sketch Scheme and Stage 2b - Detailed Design)

Stage 3 - Tender Action, Evaluation and Award

Stage 4 - Construction

* Pre-designated as an Irish-medium school