141. To ask the Minister for Education and Skills further to Parliamentary Question No. 159 of 23 June 2021, the date the tenders arrived back for a project (details supplied) following the extension of four weeks after 8 September 2021; if a timeline has been established for the awarding of tenders; and if construction will begin in quarter 4 2021. [54988/21]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The school building project referred to by the Deputy is being delivered under my Department’s Design and Build Programme.

On June 14th 2021, this project was included in a bundle of projects which were tendered to a newly established Design & Build Contractors Framework. The tenders were returned on October 27th 2021 and are currently being assessed by my Department's Project Manager.

The award of the building contract to the successful Contractor is anticipated in Quarter 1 of 2022. Once a Contractor has been appointed, my Department will keep the school informed of the construction programme underpinning the contract.

Photo of Seán SherlockSeán Sherlock (Cork East, Labour)
Link to this: Individually | In context | Oireachtas source

142. To ask the Minister for Education and Skills the status of tenders received for a project (details supplied); and the current timeline for construction to begin. [54989/21]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I would like to inform the Deputy that a tender report has not been received from the school in question in regards to the Window Project approved under the Emergency Works Scheme.