310. To ask the Minister for Public Expenditure and Reform if he has received notice from the OPW that it will miss its deadline for completion of the Garda HQ project at Military Road; the sum of the additional works that are to be completed following design detail changes; and the additional budget allocated to this project. [52906/21]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Construction of the new Garda Security and Operational Command Centre at Military Rd is progressing in a very satisfactory manner. It is on schedule to be completed on time and it is being developed within its approved total project budget.

Photo of Darren O'RourkeDarren O'Rourke (Meath East, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

311. To ask the Minister for Public Expenditure and Reform the amount that the OPW spend on the refurbishment of Navan Garda station. [53044/21]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Office of Public Works can confirm that a contract for the refurbishment of Navan Garda Station to the value of €1,638,816.32 excluding vat was awarded on 15th April 2021. The total expenditure to date for the project is €239,864.66 which includes vat and consultancy fees.

The project is co- funded by the Office of Public Works and An Garda Síochána.

Photo of Niamh SmythNiamh Smyth (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

312. To ask the Minister for Public Expenditure and Reform the timeline for the commencement of work on the new Bailieborough Garda station; and if he will make a statement on the matter. [53221/21]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The procurement phase for this project is well progressed and this phase will be completed shortly. It is expected that a contract for the works will be placed following successful completion of all procurement processes. Construction should commence shortly thereafter.