Department of Transport, Tourism and Sport

Rail Network

Photo of Joe FlahertyJoe Flaherty (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

303. To ask the Minister for Transport, Tourism and Sport further to Parliamentary Questions Nos. 28 to 31, inclusive, of 4 March 2021, the timeframe for the completion of the preliminary business case for the DART expansion project. [18262/21]

Photo of Joe FlahertyJoe Flaherty (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

304. To ask the Minister for Transport, Tourism and Sport further to Parliamentary Questions Nos. 28 to 31, inclusive, of 4 March 2021, if the DART expansion project will be announced in advance of the launch of phase two of the review of the national development plan. [18263/21]

Photo of Joe FlahertyJoe Flaherty (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

305. To ask the Minister for Transport, Tourism and Sport further to Parliamentary Questions Nos. 28 to 31, inclusive, of 4 March 2021, the length of time it will it take to complete the DART expansion project once the technical review of the DART expansion commences. [18264/21]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 303 to 305, inclusive, together.

As outlined in my response of 4 March the Public Spending Codesets out the requirements for the evaluation, planning and management of public investment projects in Ireland and the Code applies to all public bodies and to all bodies whose projects are supported by Exchequer capital funding.

The Codesets out a number of Decision Gates in the development of a project proposal; these are points where major decisions need to be made about the progress of a project and, for projects expected to cost over €100million, Government approval is required at these stages. For a project in this category, "Decision Gate 1: Preliminary Business Case" is the first stage where the Public Spending Codestipulates that formal Government approval is required.

In accordance with the Public Spending Code's requirements, the National Transport Authority has in recent days submitted the DART+ Preliminary Business Case to my Department. The Codestipulates that it must be reviewed by both my Department and the Department for Public Expenditure and Reform. Following completion of these necessary steps I will then bring the matter to Government for its decision.

The review of the National Development Plan obviously provides an opportunity to consider the funding requirements associated with the programme now that we have reached this milestone and I will certainly be engaging with my Government colleagues in that regard as that review process continues over the coming months.

In terms of delivery of DART+ itself, the Deputy is aware that the proposal is a programme comprised of various different elements primarily related to fleet expansion and then infrastructure improvements across the various lines: DART+ West, DART+ South West and DART+ Coastal. These elements will all move at slightly different times as they are all at different stages of development, with the fleet expansion and DART+ West elements the most advanced and these will be the first to be delivered, subject to Government approval of the Preliminary Business Case and of course the planning approval in relation to the infrastructure improvements.