Written answers

Wednesday, 24 February 2021

Department of Defence

Defence Forces Properties

Photo of Patricia RyanPatricia Ryan (Kildare South, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

385. To ask the Taoiseach and Minister for Defence the nature of the ongoing works at the Curragh Camp, County Kildare; the cost of same; the works planned in the next 12 months; and if he will make a statement on the matter. [10340/21]

Photo of Simon CoveneySimon Coveney (Cork South Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am advised by the Military Authorities of the following projects at the DFTC Curragh Camp that are at various stages of progression:

Project Estimated Cost Project Status

Range Upgrade and Installation of Automated Marking System €2m Commenced - Works Ongoing
New Cadet School HQ (Refurbish Old Guard room Pearse Bks) €2.5m To Commence Quarter 3 2021
Plunkett Block 1 ACS locker room facility €0.3m To Commence 2021
Ceannt 1 Block fire protection & ablution upgrade €0.3m To Commence 2021
Cadets Mess fire proofing upgrade €0.28m To Commence 2021
Sleeping Accommodation - emergency lighting Phase 1 €0.25m To Commence 2021

The Deputy may also wish to note that my Department has allocated in the region of €10m this year to the Defence Forces for the maintenance, repair and upkeep of its building stock. This devolved budget is a regular feature of the Delegated functions assigned to the Defence Forces by my Department. The individual prioritisation of specific projects to be carried out is solely a matter for the Defence Forces in keeping with the delegated nature of this budget.