Written answers
Wednesday, 24 February 2021
Department of Defence
Defence Forces Properties
Patricia Ryan (Kildare South, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
385. To ask the Taoiseach and Minister for Defence the nature of the ongoing works at the Curragh Camp, County Kildare; the cost of same; the works planned in the next 12 months; and if he will make a statement on the matter. [10340/21]
Simon Coveney (Cork South Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source
I am advised by the Military Authorities of the following projects at the DFTC Curragh Camp that are at various stages of progression:
Project | Estimated Cost | Project Status |
---|---|---|
Range Upgrade and Installation of Automated Marking System | €2m | Commenced - Works Ongoing |
New Cadet School HQ (Refurbish Old Guard room Pearse Bks) | €2.5m | To Commence Quarter 3 2021 |
Plunkett Block 1 ACS locker room facility | €0.3m | To Commence 2021 |
Ceannt 1 Block fire protection & ablution upgrade | €0.3m | To Commence 2021 |
Cadets Mess fire proofing upgrade | €0.28m | To Commence 2021 |
Sleeping Accommodation - emergency lighting Phase 1 | €0.25m | To Commence 2021 |
The Deputy may also wish to note that my Department has allocated in the region of €10m this year to the Defence Forces for the maintenance, repair and upkeep of its building stock. This devolved budget is a regular feature of the Delegated functions assigned to the Defence Forces by my Department. The individual prioritisation of specific projects to be carried out is solely a matter for the Defence Forces in keeping with the delegated nature of this budget.
No comments