43. To ask the Minister for Transport, Tourism and Sport the status of the MetroLink project; the latest cost estimate for the project; the construction timeline; if he is considering extending the line beyond Charlemont; and if he will make a statement on the matter. [7768/21]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area, including MetroLink.
Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a direct reply. Please contact my private office if you do not receive a reply within 10 days.
Darren O'Rourke (Meath East, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
44. To ask the Minister for Transport, Tourism and Sport the status of the DART+ project; the latest cost estimate for the project; the timeline for completion; and if he will make a statement on the matter. [7769/21]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area (GDA), including the DART+ programme
In light of their statutory responsibilties I have therefore referred your question to the NTA for a more detailed reply. Please contact my private office if you do not receive a reply within 10 days.