Written answers

Wednesday, 10 February 2021

Department of Justice and Equality

Garda Stations

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

660. To ask the Tánaiste and Minister for Justice and Equality the number and location of Garda stations throughout the country deemed to need refurbishment; her plans for same; and if she will make a statement on the matter. [7150/21]

Photo of Helen McEnteeHelen McEntee (Meath East, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As the Deputy will be aware, the Garda Commissioner is by law responsible for the management and control of An Garda Síochána and for the effective and efficient use of Garda resources, including all Garda stations. Further, the Office of Public Works (OPW) has responsibility for the provision and maintenance of Garda accommodation. Works in relation to Garda accommodation are therefore progressed by the Garda authorities working in close cooperation with the OPW.

I am informed by the Garda authorities that the information provided in the table below sets out projects that were in development at 22 December 2020. I have requested an up to date report from the Garda authorities which I will furnish to the Deputy once I receive it.

I am advised that the details provided focus on works of a more substantial nature that seek to replace a Garda Station, construct a new Garda Station or make a significant enhancement to the Station by way of full refurbishment or enlargement of the facility, having regard to the funding available and the competing priorities on accommodation within the Garda estate.

The details below do not outline the work conducted to maintain Garda Stations across the country or the more minor upgrade works that take place on a regular basis.

Garda Station
Description of Project
Status – as per OPW
Anglesea St GS Upgrade works to allows accommodation of Cyber Crime Unit On Site
Anglesea St GS Control Room Upgrade Works Design Stage
Athlone Refurbishment, extension and alteration of the existing station to include the adjacent former Government Buildings. Expected completion Q1/early Q2 2021. On Site
Bailieborough GS Development of new District Headquarters Moving to issue tenders
Bridewell GS Dublin Refurbishment works Design stage
Carlow GS Reconfiguration of prisoner entrance Design Stage
Cavan ASU Enhancements to Cavan Garda Station to include Accommodation for a new North Western Region Armed Support Unit and a new public office On Site
Clonmel New station to be procured as a PPP Part IX Planning permission application process
Clonmel GS Fit out of locker rooms and Fire safety works Tender Stage
Donegal Town GS Refurbishment and extension of existing Station Handover
Donnybrook GS Replacement of existing changing facilities and refurbishment of public entrance at Donnybrook GS Design Stage
Drogheda GS Provide new PEMS facility Procurement stage
Fitzgibbon St Full refurbishment of the existing station On Site
Greystones GS Refurbishment works Design stage
Henry Street Replacement of Prefabricated Units housing Locker Rooms Contract awarded
Longford GS New Cell Block and Refurbishment works at Longford Garda Station On Site
Macroom New station to be procured as a PPP Part IX Planning permission application process
Macroom GS Provision of additional temporary accommodation On site
Naas GS Provide new PEMS facility Planning stage
Navan GS Provision of a new two-storey building at Navan GS including a new cell block and additional office space Tender Stage
Newcastle West New Station to replace existing Station Design Stage
Portlaoise Refurbishment, extension and alteration of the existing station. Part IX Planning permission application process
Roscommon GS Cell Upgrade and Refurbishment Works. On Site
Sligo GS Cell upgrade and refurbishment works for the provision of a new custody suite including new cells and prisoner processing area as well as solicitor and doctor's rooms. On Site
Store St GS Reconfiguration of the ground floor of Store Street GS Design Stage
Swords GS Demolition of the existing accommodation and provision of temporary decant accommodation. On Site
Tallaght GS Provide new PEMS facility Design stage
Togher GS Fabric Upgrade and Universal Access works Tender Stage