275. To ask the Minister for Public Expenditure and Reform the Garda stations within North Dublin Garda Division that are due to be refurbished by the Office of Public Works in the first half of 2021; when each project will commence; and the time frame for the duration of same. [1199/21]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I can confirm that the Office of Public Works intends to carry out refurbishment works to the Garda Stations within the Dublin North Garda Division listed below in the first half of 2021.

Details of these works and the timeframe for the duration of the works are as outlined in the table below.

Dublin North Garda Station Refurbishment  Works to be carried out in the first half of 2021 Commencement Date Timeframe for duration of works *
Fitzgibbon St GS Completion of full refurbishment of the Station. Commenced in January 2020 currently on site. Due for completion March 2021.

Howth GS Completion of Structural repairs to roof capping and render at high level Commenced in 2020 currently on site. Due for completion February 2021
Clontarf GS Completion of conservation and repair works to facade Commenced in 2020. currently on site. Due for completion February 2021
Clontarf GS Repairs to doors, roof, and rain water goods (downpipes, eve runs etc)  to outhouses, also high level soffit and fascia to rear facade Due to commence June 2021 8 weeks
Garristown GS Refurbish/ repair shower/ WC Due to commence June 2021 4 weeks
Store Street Resurface car park deck and provide additional drainage Due to commence April 2021 8 weeks
Store Street Reconfiguration of custody area To be confirmed by client 20 weeks
Transaer House Relocation of airside fence To be confirmed by client 6 weeks

Information Note

The works outlined in the table above include works which commenced in 2020 and will continue in 2021 and also works which are due to commence in the first half of 2021.

The Commencement and completion dates may change depending on the duration of the current restrictions. 

Intermediate projects confirmed that they have no projects to include.  