Written answers

Tuesday, 1 December 2020

Department of Communications, Climate Action and Environment

National Broadband Plan

Photo of Michael McNamaraMichael McNamara (Clare, Independent)
Link to this: Individually | In context | Oireachtas source

147. To ask the Minister for Communications, Climate Action and Environment the scheduled and planned enabling of broadband exchanges in County Clare under the national broadband plan; and if he will make a statement on the matter. [39686/20]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract signed last November to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools.

In County Clare, there are 69,225 premises of which 22,592 (33%) are within the intervention area for the National Broadband Plan. The deployment plan forecasts premises passed in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years.

I am advised by NBI that, as of 23 November 2020, over 136,000 premises across all counties have been surveyed which is ahead of the full year survey target of 120,000 that had been projected by the company. Surveys have been completed in County Clare in the areas of Cratloe, Ballycannan, Ballyglas and Cloghrea and NBI indicative dates for fibre connections for premises in these areas, which are close to the border of Limerick, is mid 2021. Further surveys have recently commenced in the areas of Kilkishen, but deployment information is not yet available from NBI for this location.

Surveying is the first step towards delivering the new fibre network and involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area. This informs design solutions for provision of the fibre network to each and every premises in the surveyed area and leads to detailed designs. The detailed designs are then used to initiate the ‘make ready’ project with Open eir for the area, where Open eir ensure any poles and ducts being reused are fit for purpose and the make ready of other required infrastructure. This step also informs decisions on equipment ordering.

Survey data is also needed to initiate pre-works which pave the way for the deploying of fibre. Pre-works involve construction of new duct routes, erection of poles, building chambers, and tree trimming. On completion of these pre-works, the main construction works can commence. This involves deploying fibre overhead on poles and in underground ducts, splicing of fibre, and unblocking of ducts. Once the main construction works are completed and the appropriate level of testing has been undertaken, the fibre network can be commissioned and end users can order their connection.

Further details are available on specific areas in Clare through the NBI website which provides a facility for any premises within the intervention area to register their interest in being provided with deployment updates through its website . Individuals who register with this facility will receive regular updates on progress by NBI on delivering the network and specific updates related to their own premises when works are due to commence. I am aware that concerns have been raised regarding the level of information available on the deployment of the NBI network and I am advised that NBI is working to provide more detail on its website in this regard, with a rolling update on network build plans.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 20 November, 149 publicly accessible BCP sites have been installed by NBI, with 59 already connected to high speed broadband service. The remaining locations will be connected through service provider contracts managed by the Department of Rural and Community Development in the coming months. In Clare, Cree Community Centre, Loop Head Lighthouse and Michael Cusack Visitor Centre BCPs have been connected. A further BCP at Loughraney has had infrastructure installed by NBI and will be connected in the coming weeks.

Some 52 schools throughout Ireland have now had infrastructure installed by NBI, with 23 schools already connected to high speed broadband. In Clare, a number of schools including Shragh, Ennistymon and Stonehall National Schools are now connected as part of this initiative. My Department continues to work with Department of Education and Skills to prioritise the remaining schools to be connected over the term of the NBP. Further details can be found at .