Written answers

Wednesday, 21 October 2020

Department of Communications, Climate Action and Environment

National Broadband Plan

Photo of Thomas PringleThomas Pringle (Donegal, Independent)
Link to this: Individually | In context | Oireachtas source

24. To ask the Minister for Communications, Climate Action and Environment the number of homes which have been connected with fibre broadband since National Broadband Ireland took control of the roll out of the National Broadband Plan by county, in tabular form; and if he will make a statement on the matter. [31804/20]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract signed last November to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools.

The NBP network will offer users a high speed broadband service with a minimum download speed of 500Mbps from the outset. This represents an increase from the 150Mbps committed to under the Contract. The deployment plan forecasts premises passed in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years.

As of 13 October, design work is complete or ongoing in target townlands across 24 counties and steady progress is being made with over 103,000 premises surveyed to date. This activity is increasing week on week and by year end, NBI expects to have completed some 120,000 surveys. This activity involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area. This is informing design solutions for provision of the fibre network. This detailed design is then used to initiate the ‘make ready’ project with eir for the area, where eir ensure any poles and ducts being reused are fit for purpose. It is also used to initiate works with the subcontractors deploying the actual fibre in the area.The laying of fibre should commence shortly with the first fibre to the home connections expected around December this year.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 13 October 2020, some 164 BCP sites have been installed by NBI and 51 of these are now connected with high speed publicly accessible broadband, through a service provider contract managed by the Department of Rural and Community Development. In addition some schools will be provided with high speed broadband for educational access only through service provider contracts managed by the Department of Education and Skills.  My Department will work with Department of Education and Skills to prioritise the schools to be connected over the term of the NBP. It is anticipated that 275 BCP sites will be connected by the end of the year. Further details can be found at .

While substantial progress has been made to date, the Covid 19 pandemic has had an impact on the delivery of the fibre network. The extent of this impact is currently being assessed and NBI has committed to put in place measures to mitigate the impact in as far as possible.

The Covid 19 pandemic has also highlighted the importance of good reliable broadband to ensure that citizens across Ireland can avail of remote working, education and other essential online facilities. This is reflected in the commitments in the Programme for Government where delivery of the National Broadband Plan will be a key enabler to many of the policies envisaged particularly around increased levels of remote working.

The Programme for Government has committed to seek to accelerate the roll out of the National Broadband Plan. In this regard, my Department continues to engage with NBI to explore the feasibility of accelerating aspects of this roll out to establish the possibility of bringing forward premises which are currently scheduled in years 6 and 7 of the current plan to an earlier date. Exploring the potential to accelerate the network roll out is being undertaken in parallel with the measures required to mitigate delays arising as a result of Covid-19.