Written answers

Wednesday, 7 October 2020

Department of Communications, Climate Action and Environment

National Broadband Plan

Photo of Brendan SmithBrendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

36. To ask the Minister for Communications, Climate Action and Environment if he will consider the issues raised by a local authority (details supplied) on infrastructure; and if he will make a statement on the matter. [29216/20]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract signed on 19 November last to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the nearly 540,000 premises, including almost 100,000 businesses and farms along with 695 schools.The NBP network will offer users a high speed broadband service with a minimum download speed of 500Mbps from the outset. This represents an increase from the 150Mbps committed to under the Contract. The deployment plan forecasts premises passed in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years.

Design work is complete or ongoing in target townlands across 23 counties and steady progress is being made with over 98,000 premises surveyed as of the 28 September. This survey work is feeding into detailed designs for each deployment area and laying fibre should commence shortly with the first fibre to the home connections expected before the end of the year.

In Monaghan surveys have commenced, with over 4,300 premises surveyed to date. Surveyors were working in areas such as Cornacassa, Cortolvin, Ballybay and Stranooden and other areas which will be surveyed include Mullinahinch, Bellanode, Drumhilock, Tydavnet, Cloughnart, Scotstown and Killymarley. This involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area.Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. Some 155 BCP sites have been installed by NBI and the high speed broadband service will be switched on in these locations through 'service provider' contracts managed by the Department of Rural and Community Development for publicly available sites and by the Department of Education and Skills for schools.

There are a number of BCPs located across County Monaghan where the public will be able to benefit from this service including Corcaghan, Carn, Saint Alphonsus and Mullyash Community Centres, Tannagh Outdoor Education centre, the Corduff and Latton Resource Centres as well as the Monaghan GAA centre of Excellence and Geraldines GAA Club. Further details can be found at .

A number of schools including Drumcorrin and Drumgossatt National Schools will also be connected to high speed broadband for educational access as part of the BCP initiative. My Department will work with the Department of Education and Skills to prioritise the remaining schools to be connected over the term of the NBP.

While substantial progress has been made to date, the Covid 19 pandemic has had an impact on the delivery of the fibre network. The extent of this impact is currently being assessed and NBI has committed to put in place measures to mitigate the impact in as far as possible. The Covid 19 pandemic has also highlighted the importance of good reliable broadband to ensure that citizens across Ireland can avail of remote working, education and other essential online facilities. This is reflected in the commitments in the Programme for Government where delivery of the National Broadband Plan will be a key enabler to many of the policies envisaged particularly around increased levels of remote working.

The Programme for Government has committed to seek to accelerate the roll out of the National Broadband Plan. In this regard, my Department continues to engage with NBI to explore the feasibility of accelerating aspects of this rollout to establish the possibility of bringing forward premises which are currently scheduled in years 6 and 7 of the current plan to an earlier date. Exploring the potential to accelerate the network rollout is being undertaken in parallel with the measures required to mitigate delays arising as a result of Covid-19.

Photo of Niall CollinsNiall Collins (Limerick County, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

37. To ask the Minister for Communications, Climate Action and Environment if he will request that the national broadband plan provider set out a scheduled installation timeframe on a postcode basis; if he will establish when a property (details supplied) might expect to receive a service under the National Broadband Plan. [29220/20]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

NBI provides a facility for any premises within the AMBER area to register their interest in being provided with deployment updates through its website (). This provides anyone living in the NBP intervention area with a mechanism through which they can ensure they will be updated when the network is being built out in their area. The Question refers to a premises which is located in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map which is available on my Department's website at . The AMBER area represents the area to be served by the network to be deployed under the NBP State led intervention, the contract for which was signed in November last with National Broadband Ireland (NBI). 

The NBP network will offer users a high speed broadband service with a minimum download speed of 500Mbps from the outset. This represents an increase from the 150Mbps committed to under the Contract. The deployment plan forecasts premises passed in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years.

As of 28 September, design work is complete or ongoing in target townlands across 23 counties and steady progress is being made with over 98,000 premises surveyed to date. This activity is increasing week on week and NBI expects to have completed some 120,000 surveys by the end of the year. This activity involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area. This is informing design solutions for provision of the fibre network. This detailed design is then used to initiate the ‘make ready’ project with eir for the area, where eir ensure any poles and ducts being reused are fit for purpose. It is also used to initiate works with the subcontractors deploying the actual fibre in the area. The laying of fibre should commence shortly with the first fibre to the home connections expected around December this year.

In Clare, 4,891 premises have been surveyed to date and network designs completed to deliver the new fibre network. Surveys have commenced in the areas of Cratloe, Ballycannan, Ballyglas and Cloghrea and further surveys due to commence in the areas of Kilkishen before the end of this year. This will enable design solutions for the provision of a fibre network to premises in the Intervention Area.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. Some 155 BCP sites have been installed by NBI and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development for publicly available sites and by the Department of Education and Skills (DES) for schools. 

There are a number of BCPs located across County Clare including at Caherconnell, Cree Community Centre, Loop Head and Michael Cusack Visitor Centre.  A number of schools  including Kilmurry McMahon, Shragh, Ennistymon and Stonehall National Schools will also be connected to high speed broadband as part of the BCP initiative.  Further details can be found at . The Department will work with DES to prioritise the remaining schools to be connected over the term of the NBP.

While substantial progress has been made to date, the Covid 19 pandemic has had an impact on the delivery of the fibre network. The extent of this impact is currently being assessed and NBI has committed to put in place measures to mitigate the impact in as far as possible.The Covid 19 pandemic has also highlighted the importance of good reliable broadband to ensure that citizens across Ireland can avail of remote working, education and other essential online facilities. This is reflected in the commitments in the Programme for Government where delivery of the National Broadband Plan will be a key enabler to many of the policies envisaged particularly around increased levels of remote working.

The Programme for Government has committed to seek to accelerate the roll out of the National Broadband Plan. In this regard, my Department continues to engage with NBI to explore the feasibility of accelerating aspects of this rollout to establish the possibility of bringing forward premises which are currently scheduled in years 6 and 7 of the current plan to an earlier date. Exploring the potential to accelerate the network rollout is being undertaken in parallel with the measures required to mitigate delays arising as a result of Covid-19.