Written answers

Wednesday, 9 September 2020

Department of Public Expenditure and Reform

Flood Relief Schemes

Photo of Catherine ConnollyCatherine Connolly (Galway West, Independent)
Link to this: Individually | In context | Oireachtas source

112. To ask the Minister for Public Expenditure and Reform if funding will be made available for flood defences for Tawin Island, County Galway; if so, when such funding will be available; if a Natura 2000 impact statement has been completed; and if he will make a statement on the matter. [22720/20]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I have been advised by the Office of Public Works that an application submitted under the OPW Minor Flood Mitigation Works and Coastal Protection scheme by Galway County Council for a project at Tawin, Maree, Co. Galway is currently under consideration. Further information has been requested from the Council to complete the assessment. If the application satisfies all the eligibility criteria of the Scheme, the Council will be funded 90% of the costs of the application. One such requirement is that the proposed works do not have a significant negative effect on the environment, during or after construction, and that any legislative requirements for assessment in this respect (e.g. Wildlife, Habitats, Fisheries, Environmental Impact Assessment, etc.) are fully complied with in the process.

Photo of Catherine MurphyCatherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

113. To ask the Minister for Public Expenditure and Reform the number of flood relief projects undertaken by the OPW in the past five years to date by location; the date on which each flood relief project will be completed; the associated costs of each; if projects are overdue; and if projects went to conciliation, in tabular form. [22742/20]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The table below (Table 1) sets out the information requested by the Deputy on flood relief projects that have commenced construction since the start of 2016. The information provided includes flood relief projects undertaken by the Office of Public Works (OPW), and / or Local Authorities with funding provided by OPW.

Table 1

Flood Relief Schemes which commenced construction since start 2016

Scheme Location Completion date or (substantial completion) Cost to date Estimated Final Cost (including ongoing maintenance) Is project on schedule? Did Project go to Conciliation?
Ashbourne, Co Meath Mid 2021 €3.1m €4.9m Slight delay due to Covid-19 construction restrictions No
Athlone, Co Westmeath Early 2022 €6.8m €12m Slight delay due to Covid-19 construction restrictions No
Bandon, Co Cork End 2020 (substantial completion) €27m €31.6m Scheme completion is a year behind schedule Yes
Bellurgan, Co Louth 2018 €0.7m €0.7m Yes - completed No
Claregalway, Co Galway End 2019 (substantial completion) €10.6m €11m The scheme was substantially completed a year behind schedule No
Clonakilty, Co Cork End 2020 €23.1m €29.9m Slightly be behind schedule Yes
Douglas, Cork City Early 2022 €6m €22.7m Slight delay No
Dunkellin River, Co Galway End 2019 (substantial completion) €8.4m €9m Yes – it was substantially completed in line with expectation
Ennis South, Co Clare Mid 2021 €7.2m €22.9m Yes No
Foynes, Co Limerick 2017 €2.6m €2.6m Yes - completed Yes
Lower Morell, Co Kildare 2024 €0.6m €12m Delayed by approx. 2 years due to Judicial Review No
Northlands, Co Meath 2018 (Substantial completion) €2.6m €2.6m Yes – substantial completion was reached in line with expectation No
Skibbereen, Co Cork End 2018 (substantial completion) €32.2m €38m Yes – substantial completion was reached in line with expectation Yes
Templemore, Co Tipperary Early 2021 €6m €10.2m Delayed approximately one year due to landowner issues, Covid-19 construction restrictions, weather and ground conditions No

The above projects are part of the Programme of approximately 150 capital projects being progressed as part of the National Development Plan 2018-2027, of which approximately 120 can be considered ‘major projects’ with an individual estimated total value of over €1m.

OPW also provides funding to Local Authorities to carry out minor works under the Minor Flood Mitigation Works & Coastal Protection Scheme. The Scheme provides up to €750,000 to Local Authorities to meet 90% of the cost of engineering solutions to local flooding issues. Table 2 below sets out information on this Scheme since the start of 2016.

Table 2

Minor Flood Mitigation Works & Coastal Protection Scheme

Year Funding Approved Amounts Paid to Local Authorities Number of approved projects Number of completed projects*
2016 €4.374m €2.978m 83 54
2017 €3.060m €2.398m 63 55
2018 €5.702m €1.816m 67 44
2019 €4.751m €4.406m 49 47
2020 €1.322m €0.189m 34 4
Totals €19.209m €11.787m 296 204

*Completed projects refer to projects that were completed in that year but not necessarily approved in that year.

Comments

No comments

Log in or join to post a public comment.