332. To ask the Minister for Public Expenditure and Reform if construction on the new forensic science laboratory has started; the timeframe for the completion of the project; and the estimated cost of the project. [15266/20]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The construction on the new Forensic Science Ireland Laboratory project is being managed by the OPW. The project commenced on site in March 2020 and the construction contract duration is just over 2 years. The construction Contract Value is €79.69m ex vat.