Written answers

Tuesday, 16 June 2020

Department of Housing, Planning, and Local Government

Social and Affordable Housing

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

1082. To ask the Minister for Housing, Planning, and Local Government the number of houses made available for allocation to suitable housing applicants by Kildare County Council or via approved housing bodies through Part 8, purchase and-or direct build in each of the past three years; and if he will make a statement on the matter. [11496/20]

Photo of Eoghan MurphyEoghan Murphy (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The number of social housing homes delivered in Co. Kildare has grown exponentially since the outset of Rebuilding Ireland in 2016.

Table 1 outlines a breakdown of Build Delivery in Co. Kildare of the three years requested.

Table 1: Overall Build Delivery (Co. Kildare) 2017-2019

Kildare County Council LA New Build AHB New Build Part V -New Build (All delivery streams) Total New Build LA Capped Voids All Build Total
2017 28 66 24 118 8 126
2018 65 76 84 225 9 234
2019 128 171 154 453 0 453
Totals 221 313 262 796 17 813

Table 2 give a breakdown of the number of Turnkeys delivered within the overall Build Total.

Table 2: Turnkey Delivery (Co. Kildare) 2017-2019

Kildare County Council AHB Turnkeys LA Turnkeys Total Turnkeys All Build Total
2017 66 22 88 126
2018 131 39 170 234
2019 257 78 335 453
Totals 454 139 593 813

Table 3 outlines the additional Acquisitions and Leasing outputs which delivered social homes in Co. Kildare over the period 2017-2019 inclusive.

Table 3: Social Housing Acquisitions and Leasing Outputs (Co. Kildare) 2017-2019

Kildare County Council LA Acquisition AHB Acquisition Acquisition Total Leasing Total
2017 108 141 249 53
2018 164 68 232 24
2019 241 30 271 24
Totals 513 239 752 101

Overall the number of social homes delivered through Build, Acquisition and Leasing over the past three years is 1,666 homes. Since, Rebuilding Ireland launched in 2016, almost 2,000 (1,919) social homes have been provided in by Kildare County Council in partnership with Approved Housing Bodies and we are committed to see this number grow over this year and going forward.