Written answers
Tuesday, 9 June 2020
Department of Housing, Planning, and Local Government
Local Authority Housing
Cian O'Callaghan (Dublin Bay North, Social Democrats)
Link to this: Individually | In context | Oireachtas source
721. To ask the Minister for Housing, Planning, and Local Government the average construction and all-in cost of building 1, 2, 3 and 4-bedroom public houses by region including Dublin, Cork, Galway, Limerick and Waterford cities and surrounding commuter and non-urban areas; and if he will make a statement on the matter. [10392/20]
Eoghan Murphy (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source
There are a number of variables involved in estimating the cost of providing social housing units, such as the form of delivery, size of unit, land, funding, etc. In terms of construction and 'all-in' costs, the averages as sought for the various sized units, based on full capital costs, are set out in the following tables, where the data is shown in terms of houses and apartments, both for Dublin and nationally.
HOUSES - DUBLIN | |||||
---|---|---|---|---|---|
1 bed | 2 bed(1 storey) | 2 bed(2 storey) | 3 bed | 4 bed | |
Construction | €197,850 | €207,975 | €216,975 | €227,275 | €243,125 |
All-in Cost | €258,450 | €270,575 | €280,675 | €292,500 | €311,325 |
APARTMENTS - DUBLIN | |||
---|---|---|---|
1 bed | 2 bed | 3 bed | |
Construction | €221,450 | €238,625 | €261,425 |
All-in Cost | €289,250 | €310,425 | €338,150 |
HOUSES - NATIONALLY | |||||
---|---|---|---|---|---|
1 bed | 2 bed(1 storey) | 2 bed(2 storey) | 3 bed | 4 bed | |
Construction | €155,818 | €165,132 | €174,206 | €184,685 | €199,491 |
All-in Cost | €201,359 | €212,624 | €222,582 | €234,571 | €252,047 |
APARTMENTS - NATIONALLY | |||
---|---|---|---|
1 bed | 2 bed | 3 bed | |
Construction | €174,159 | €189,112 | €209,482 |
All-in Cost | €225,082 | €243,476 | €267,629 |
The above figures are based on returned data from tendered social housing schemes over an extended period. ‘Construction’ cost is reflective of building costs (including VAT) and also includes normal site works and site development. ‘All-in Cost’ includes cost of construction, land cost, professional fees, utility connections, site investigations/surveys, archaeology where appropriate, VAT and contribution to public art. Abnormal costs are excluded from these figures.