Written answers
Wednesday, 13 May 2020
Department of Public Expenditure and Reform
Garda Stations
Catherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source
146. To ask the Minister for Public Expenditure and Reform the current status of conciliation under way in respect of the new Kevin Street Garda station and Galway Garda station; the costs incurred to date as a result of the conciliation processes; if other Garda buildings projects are in conciliation; and if he will make a statement on the matter. [5106/20]
Kevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context | Oireachtas source
The conciliation process for Kevin Street Garda Station is not yet concluded. Conciliation costs paid to date are €329,542.79, Vat. inclusive. The Galway Garda Station conciliation process is still ongoing and conciliation costs paid to date are €89,619.85, Vat inclusive. No other Garda projects have entered into the conciliation process.
No comments