Garda Station Refurbishment

Photo of Catherine MurphyCatherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

124. To ask the Minister for Public Expenditure and Reform if a schedule will be provided of works for each Garda station in the context of planned retrofitting and-or renovation works in 2020, 2021 and 2022; the status of Fitzgibbon Street station as of 27 February 2020; and if he will make a statement on the matter. [2971/20]

Photo of Kevin  MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context | Oireachtas source

The final phase of the refurbishment works for Fitzgibbon St commenced in January this year and are scheduled to take 12 months to complete.

Please see below a list of Garda Stations refurbishments, which exceed €250,000 in value, and which are scheduled to be carried out during the period 2020 to 2022.

Garda Station Year of proposed works
Bailieborough GS 2021/2022
Athlone GS 2020/2021
Portlaoise GS 2020/2021/2022
Fitzgibbon St GS 2020/2021
Donegal GS 2020
Bawnboy GS 2020
Leighlinbridge GS 2020
Bridewell GS, Dublin 2021/2022
Greystones GS 2021/2022
Henry Street GS, Limerick 2020
Carlow GS 2020
Swords GS 2020
Dungarvan GS 2020
Longford GS 2020/2021
Roscommon GS 2020/2021
Navan GS 2020/2021/2022
Finglas GS 2020
Listowel GS 2020/2021
Sligo GS 2020
Cavan GS 2020
Youghal GS    2020/2021
Thomastown GS 2020/2021
Clonmel GS 2020/2021