113. To ask the Minister for Public Expenditure and Reform the status and completion date for construction works at the new Bailieborough Garda station; and if he will make a statement on the matter. [2861/20]

Photo of Kevin  MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context | Oireachtas source

The pre-qualification procedure for the main contractor is ongoing.  Pre-qualification of the reserved specialists will begin shortly.  It is expected that tenders will issue for the construction work during this summer with a contract awarded before the end of the year.  Construction will take about 18 months.