Written answers

Tuesday, 17 December 2019

Department of Education and Skills

Schools Building Projects Data

Photo of John CurranJohn Curran (Dublin Mid West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

236. To ask the Minister for Education and Skills the details of each school that recently progressed to the next stage of architectural planning, stage 3 tender phase and that had previously been at stage 2B for a considerable period of time; and if he will make a statement on the matter. [53259/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The following spreadsheet details the 13 projects that have progressed from an advanced stage of architectural planning - Stage 2(b), Detailed Design to the next stage of architectural planning - Stage 3, Tender Stage since the start of the 2019/20 academic year.

Thereafter, a tender stage normally takes between 7 and 8 months to complete depending on the size and complexity of the project.

Major Projects progressed to Stage 3 (Tender) since 1st September 2019
Project Type & Delivery County Roll No School Date progress to Stage 3 (Tender Stage)
Major Projects - TRAD Donegal 19313C Glenswilly NS 06/09/2019
Donegal 18625Q Scoil Cholmcille, Letterkenny 27/09/2019
Donegal 19927O St. Mary's, Stranorlar 27/09/2019
Mayo 64520M St. Mary's, Ballina 01/10/2019
Kildare 16706G St. Joseph's, Kilcock 26/09/2019
Kildare 61702D St. Paul's Monasterevin 26/09/2019
Wicklow 61830M St. David's, Greystones 11/12/2019
Major Projects - ADAPT Cork 6209D Scoil Mhuire Gan Smál, Blarney 18/11/2019
Kildare 17872F & 17873H St. Conleth & St. Mary's, Newbridge 18/10/2019
Tipperary 18716T Cahir 12/12/2019
Dublin 20176C Rush & Lusk 04/11/2019
Major Projects - Devolved Cork 14052V Kanturk BNS (S-B) (with RN 17087J) 07/11/2019
Dublin 20131D Dublin 7 ETNS End Aug/Early Sep 2019

Photo of John CurranJohn Curran (Dublin Mid West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

237. To ask the Minister for Education and Skills the number of school building projects at stage 2B detailed design; the number that have been at this stage for up to one, one to three, three to five, five to seven, seven to ten and over ten years, respectively; and if he will make a statement on the matter. [53260/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In terms of current projects at Stage 2(b) - Detailed Design, 22 projects have recently been approved to Stage 2(b) and are at this latter stage of architectural planning for less than 1 year, 21 such projects have been progressing through the stage from 1-3 years, 12 projects have been progressing from 3-5 years, 9 further projects have been progressing from 5-7 years and 2 projects have been progressing through the stage from 7-10 years.

This is in the context of currently over 60 major school building projects at this advanced stage of architectural planning and a continuous throughput of projects moving into Stage 2(b) and onwards to Tender Stage and Construction.