Written answers

Thursday, 28 November 2019

Department of Communications, Climate Action and Environment

National Broadband Plan Implementation

Photo of Charlie McConalogueCharlie McConalogue (Donegal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

22. To ask the Minister for Communications, Climate Action and Environment the status of the commitment to provide high speed broadband to every house and business in County Donegal; the timeline for when the roll-out will commence in the county; and if he will make a statement on the matter. [49346/19]

Photo of Charlie McConalogueCharlie McConalogue (Donegal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

27. To ask the Minister for Communications, Climate Action and Environment the status of the national broadband plan; when all homes and businesses in County Donegal will have access to high speed broadband; and if he will make a statement on the matter. [49345/19]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 22 and 27 together.

The National Broadband Plan is the Government’s plan to rollout high speed broadband to the 1.1 million people living and working in the nearly 540,000 premises including almost 100,000 businesses and farms, along with 695 schools, where commercial operators will not commit to deliver the service.

Following the contract signing on 19 November, work has already begun and a deployment plan will be made available by NBI shortly. All counties will see premises passed in the first 2 years and over 90% of premises in the State will have access to high speed broadband within the next four years.

Approximately 300 Broadband Connections Points (BCPs), including schools, library hubs and local sports halls in every county in Ireland, including Co. Donegal, will be connected to high speed broadband during 2020, to enable communities to quickly get free public access to high speed broadband. 12 BCPs are planned for deployment in Donegal. The BCP locations are available to view on the High Speed Broadband Map on the Department’s website www.dccae.gov.ie.

By the end of 2021, NBI plans to pass approximately 115,000 premises, with 70,000 - 100,000 passed each year thereafter until rollout is completed. NBI has indicated that the network rollout will take an estimated 7 years from the beginning of deployment.

The planned rollout will provide access to high speed broadband to 32,130 premises located in the Intervention Area in Donegal through investment of approximately €128m over 25 years.