Written answers

Thursday, 17 October 2019

Department of Education and Skills

Schools Building Projects Data

Photo of John CurranJohn Curran (Dublin Mid West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

64. To ask the Minister for Education and Skills the number of school building projects at stage 2B detailed design; the number that have been at this stage for up to one, one to three, three to five, five to seven, seven to ten and more than ten years, respectively; and if he will make a statement on the matter. [41420/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In terms of current projects at Stage 2(b) - Detailed Design, 19 projects have recently been approved to Stage 2(b) and are at this latter stage of architectural planning for less than 1 year, 28 such projects have been progressing through the stage from 1-3 years, 15 projects have been progressing from 3-5 years, 8 further projects have been progressing from 5-7 years and 2 projects have been progressing through the stage from 7-10 years.

This is in the context of currently over 70 major school building projects in advanced architectural planning and a continuous throughput of projects moving into Stage 2(b) and onwards to Tender Stage and Construction.