Written answers
Tuesday, 15 October 2019
Department of Education and Skills
Schools Building Projects Status
Fiona O'Loughlin (Kildare South, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
222. To ask the Minister for Education and Skills the status of an extension for a school (details supplied) in County Kildare. [42077/19]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The project referred to by the Deputy has been devolved for delivery to the National Development Finance Agency (NDFA).
I am pleased to inform the Deputy that the process for the appointment of a programme manager and design team for the project is well underway.
While at this early stage it is not possible to provide a timeline for completion of the project, the NDFA will be engaging directly with the school authority to keep it informed of progress.
Fiona O'Loughlin (Kildare South, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
223. To ask the Minister for Education and Skills his plans for the proposed extension of a school (details supplied); the status of the project; the timeline for completion of the works; and if he will make a statement on the matter. [42078/19]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
This building project is included in my Department’s Construction Programme which is being delivered under the National Development Plan.
The project is currently at Stage 2B of the Architectural Planning process – Detailed Design Stage which includes securing statutory approvals and the preparation of tender documents. The pre-qualification of contractors process to compile a shortlist of suitable contractors is complete and tender documentation is being finalised.
Stage 2(b) Detailed Design is arguably the most complex and detailed of all the stages in Architectural Planning. In addition to securing the necessary statutory approvals it also includes the preparation of complex and detailed tender documents. In completing Stage 2(b), Design Teams are now required to upgrade design details to ensure that new school buildings are Near Zero Energy Buildings (NZEB) in compliance with the 2017 amendment to Part L of the current Building Regulations.
The next step for this project is Stage 3 – tender stage which normally takes 7-8 months to complete. My Department will be in contact shortly with the school and Design Team regarding the progression of this project.
No comments