Written answers

Thursday, 3 October 2019

Department of Communications, Climate Action and Environment

National Broadband Plan

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

288. To ask the Minister for Communications, Climate Action and Environment when he expects to sign the contract for the national broadband plan; the roll out timetable in terms of the number of premises to be connected in each quarter of 2020 and 2021; the number expected to be connected at the end of 2021; and if he will make a statement on the matter. [40466/19]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Every home, farm, school and business in Ireland will have access to high speed broadband – no matter where they are located – following the Government’s decision to approve the appointment of a preferred bidder to the National Broadband Plan. Under this plan, Ireland will become one of the first countries in the world to ensure that those in rural areas have the same digital opportunities as those in urban areas. This is being achieved through a combination of commercial investment across the country, and a State intervention in those areas where commercial operators acting alone are unlikely to invest. The NBP has been a catalyst in encouraging investment by the telecoms sector. In 2012, less than 700,000, or 30% of Irish premises had access to high speed broadband. Today, 74% of the 2.4 million premises in Ireland can access high speed broadband.

The goal of the National Broadband Plan intervention is to engage a company to build, operate and maintain the NBP State intervention network.

The Government decision on 7 May 2019 means that it is intended to award the State Intervention contract to National Broadband Ireland, subject to contract close, including the finalisation of financial and legal documents. Deployment of the NBP State Intervention network will commence shortly after that.

The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment.

A deployment plan will be made available by the Bidder once the contract is signed. In the first year of roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations.

The Bidder is aiming to pass 133,000 premises at the end of the second year, with 70-100,000 passed each year thereafter until roll out is completed.

Work continues on finalising the contract and in parallel to this work, I am considering the recommendations of the Joint Oireachtas Communications Committee report which was published recently. I will bring my deliberations of the report to Government in due course.