134. To ask the Minister for Health the estimated cost of the national children’s hospital and ancillary facilities; the amount paid to date; the expected amount that will be paid between now and the completion of the project; and if he will make a statement on the matter. [40399/19]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I advised Government in December 2018 that the final cost of the design, build and equipment programme for which the National Paediatric Hospital Development Board is responsible for is now at €1,433 million. There has been no change to this figure advised to Government.

The construction phase of the project is underway. The main hospital is scheduled to be completed by late 2022 and, following a period of commissioning, is expected to open to patients in 2023.

The total capital expenditure on the new children's hospital project from 2013 to end September 2019 is €385.13m.