Infrastructure and Capital Investment Programme

Photo of Peadar TóibínPeadar Tóibín (Meath West, Aontú)
Link to this: Individually | In context | Oireachtas source

97. To ask the Minister for Transport, Tourism and Sport the details of each State infrastructure project that is in development or is due for completion in 2019 in which it is in excess of the budget assigned to the project for its current stage to date. [39522/19]

Photo of Shane RossShane Ross (Dublin Rathdown, Independent)
Link to this: Individually | In context | Oireachtas source

As Minister for Transport, Tourism and Sport, I have responsibility for policy and overall funding in relation to public transport and roads.

The National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area and our regional cities. Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a direct reply. Please contact my private office if you do not receive a reply within 10 days.

The improvement and maintenance of regional and local roads is the statutory responsibility of the relevant local authority in accordance with the provisions of Section 13 of the Roads Act 1993. Works on those roads are funded from the Council's own resources supplemented by State road grants. Each local authority is the contracting authority for the purpose of implementation of regional and local road improvement projects.

In the case of national roads Transport Infrastructure Ireland in conjunction with the relevant local authority is responsible for the implementation of road improvement schemes.

I would point out that cost estimates for road improvement schemes are reviewed at project development milestones and allowing for cost inflation and project implementation risks are subject to change. The Total Scheme Budget at the point of the award of the main construction contract forms the basis for assessing the cost outturn once the final account for a scheme is settled.

In relation to the road PPP projects, the PPP company is responsible for construction and carries the budget risk for the project.

The details for road projects in development or completion in 2019 are included in the following table.

NATIONAL ROADS
SCHEME NAMEESTIMATE STAGEBUDGET OUTTURN
AT CONSTRUCTION IN 2019
N11 Gorey Enniscorthy PPP (Scheme Open)Construction EstimateConstruction Risk with PPP Co.
N25 New Ross Bypass PPPConstruction EstimateConstruction Risk with PPP Co.
M7 Naas Road WideningConstruction EstimateFinal Account TBD
N56 Mountcharles to InverConstruction EstimateFinal Account TBD
N56 Dungloe to GlentiesConstruction EstimateFinal Account TBD
N4 Collooney to CastlebaldwinConstruction EstimateFinal Account TBD
SCHEMES PROGRESSING TO CONSTRUCTION
N5 Westport to TurloughFinal Business Case Cost EstimateTo be determined
N22 Ballyvourney to MacroomFinal Business Case Cost EstimateTo be determined
SCHEMES INTENDING TO GO TO TENDER
M8/N25 DunkettleTBD for Final Business CaseTo be determined
N69 Listowel BypassTBD for Final Business CaseTo be determined
N52 Ardee BypassTBD for Final Business CaseTo be determined
N5 Ballaghaderreen to ScramogeTBD for Final Business CaseTo be determined
N59 Moycullen BypassTBD for Final Business CaseTo be determined
INTENDING TO PROCEED TO PLANNING APPROVAL
N21/N69 Limerick to Foynes, incorporating the Adare BypassBusiness Case Cost EstimateTo be determined
SUBJECT TO JUDICAL REVIEW POST STATUTORY PROCESS
N28 Cork to RingaskiddyBusiness Case Cost EstimateTo be determined
REGIONAL & LOCAL ROADS
AT CONSTRUCTION/CONSTRUCTION COMPLETED
R407 Sallins BypassConstruction EstimateFinal Account TBD
Adamstown & Nangor Road UpgradeConstruction EstimateFinal Account TBD
Sligo Western Distributor RoadConstruction EstimateFinal Account TBD
Portlaoise Southern Distributor RoadConstruction EstimateFinal Account TBD
Dingle Relief RoadConstruction EstimateFinal Account TBD
SCHEMES PRE MAIN CONSTRUCTION TENDER STAGE
Coonagh to KnockalisheenTBD for Final Business CaseTo be determined
Athy Southern Distributor RoadTBD for Final Business CaseTo be determined
Eastern Garavogue Bridge & Approach RoadTBD for Final Business CaseTo be determined
R498 Latteragh Re-alignmentTBD for Final Business CaseTo be determined
Tralee Northern Relief RoadTBD for Final Business CaseTo be determined
R150 Bettystown to LaytownTBD for Final Business CaseTo be determined
Shannon Crossing/Killalloe By-pass/R494 UpgradeTBD for Final Business CaseTo be determined