Coastal Erosion

Photo of Brendan  RyanBrendan Ryan (Dublin Fingal, Labour)
Link to this: Individually | In context | Oireachtas source

154. To ask the Minister for Public Expenditure and Reform the position regarding the need for a permanent solution to the coastal erosion in The Burrow, Portrane, County Dublin; when he will receive a recommendation from Fingal County Council on the preferred permanent solution to address the issue; and if he will make a statement on the matter. [39425/19]

Photo of Kevin  MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context | Oireachtas source

I am advised, in respect of coastal erosion at the Burrow, Portrane, County Dublin, that Fingal County Council is leading on this issue, as it is a matter for local authorities in the first instance to assess and address problems of coastal erosion in their areas.  Where necessary, Local Authorities may put forward proposals to relevant central Government Departments, including the OPW, for funding of appropriate measures depending on the infrastructure or assets under threat.

In 2018, in response to serious coastal erosion problems at The Burrow, Portrane, Fingal County Council implemented temporary interim emergency measures to protect properties at risk.  Funding of €456,464 was approved under the OPW Minor Flood Mitigation Works and Coastal Protection Scheme for these works.

Consultants appointed by Fingal County Council are currently assessing options for a longer term permanent solution for the Portrane Penisula/Rogerstown Outer Estuary area. I have also been informed by Fingal County Council that the assessment of options will be followed by extensive public consultation, and environmental assessment and consent processes, which are likely to take several months to conclude.  The Council has further confirmed that it is probable therefore that the study, and the associated approved plan for the peninsula, will take at least until the middle of 2020 to complete.

If a viable option is identified, the Council may submit a further application for funding to the OPW or other Government Departments as appropriate.