Written answers

Wednesday, 25 September 2019

Department of Education and Skills

Schools Building Projects Status

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

84. To ask the Minister for Education and Skills the status of the provision of a new school building project for a school (details supplied); if the acquisition of a new site for the school has been completed; and if he will make a statement on the matter. [38991/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As the Deputy is aware the building project for the school in question is included on my Department's capital programme.

I am pleased to inform the Deputy that agreement in principle has been reached on the proposed acquisition of a site that will accommodate both the school to which he refers and permanent accommodation for a local primary school. This acquisition is currently progressing through the conveyancing stage and my officials are working to bring it to a conclusion at the earliest possible date.

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

85. To ask the Minister for Education and Skills the position regarding progress on a permanent school building project for a school (details supplied); and if he will make a statement on the matter. [38992/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy is currently at an advanced stage of Architectural Planning, Stage 2b - Detailed Design, which includes the application for statutory approval and the preparation of tender documents. Statutory approvals in relation to the permanent new school build have been secured.

Following the appointment of a replacement consultant architect, the Design Team has reviewed the previous Stage 2(b) documentation and is currently upgrading the design to ensure that the new school building is a Near Zero Energy Building (NZEB) in compliance with the 2017 amendment to Part L of the Building Regulations.

The Design Team is also finalising the detail in relation to the provision of temporary accommodation and playground facilities during the construction of the new school building. My Department is currently reviewing a report in relation to costs for the temporary accommodation and playground. Upon review and approval of costs, the Design Team will then submit an application for Planning Permission for the temporary accommodation and playground to the Local Authority.

The Design Team will then complete the tender documents and submit the Stage 2b report to my Department. Upon receipt and review of the Stage 2(b) submission, my Department will revert to the Board of Management regarding the further progression of the project at that time.

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

86. To ask the Minister for Education and Skills the position regarding progress on a new school building project for a school (details supplied); and if he will make a statement on the matter. [38993/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Deputy will be aware that a building project for the school to which he refers is included in my Department's School Building Programme to be delivered as part of the National Development Plan (NDP).

A new site is required to facilitate this development and my Department has recently reached agreement in principle with the landowners for the acquisition of a site. In tandem with the site acquisition, my Department will now initiate the preparation of the project brief. My Department will be in contact with the school authority when this process has been completed.

Comments

No comments

Log in or join to post a public comment.