Written answers
Thursday, 19 September 2019
Department of Transport, Tourism and Sport
Road Projects Status
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
200. To ask the Minister for Transport, Tourism and Sport if the N56 Dungloe to Glenties project has been completed; if not, when it is expected to be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38044/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
201. To ask the Minister for Transport, Tourism and Sport if the N56 Mountcharles to Inver Road project has been completed; if not, when it is expected to be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38045/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
207. To ask the Minister for Transport, Tourism and Sport if the M11 Gorey to Enniscorthy motorway public private project has been completed; if not, when it is expected to be completed; the cost of the PPP; the amount spent to date; and if he will make a statement on the matter. [38053/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
209. To ask the Minister for Transport, Tourism and Sport if the N25 New Ross bypass public private project has been completed; if not, when it is expected to be completed; the cost of the PPP; the amount spent to date; and if he will make a statement on the matter. [38055/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
210. To ask the Minister for Transport, Tourism and Sport if the N22 Ballyvourney to Macroom capital project has commenced; if so, the stage the project is at; when the project is expected to go out for tender; when construction will commence; when the project will be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38075/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
213. To ask the Minister for Transport, Tourism and Sport if the Listowel bypass capital project has commenced; if so, the stage the project is at; when the project is expected to go out for tender; when construction will commence; when the project will be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38078/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
215. To ask the Minister for Transport, Tourism and Sport the stage the M8/N4/N25 Dunkettle interchange project is at; when the project will go out for tender; when construction will commence; when the project will be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38092/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
216. To ask the Minister for Transport, Tourism and Sport the stage the N4 Collooney to Castlebaldwin project is at; when the project will go out for tender; when construction will commence; when the project will be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38093/19]
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
217. To ask the Minister for Transport, Tourism and Sport the stage the Ardee bypass project is at; when the project will go out for tender; when construction will commence; when the project will be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38094/19]
Shane Ross (Dublin Rathdown, Independent)
Link to this: Individually | In context | Oireachtas source
I propose to take Questions Nos. 200, 201, 207, 209, 210, 213, 215 to 217, inclusive, together.
As Minister for Transport, Tourism & Sport, I have responsibility for overall policy and funding in relation to the national roads programme. Under the Roads Acts 1993-2015, the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned.
Noting the above position, I have referred the questions to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.