137. To ask the Minister for Health if the National Rehabilitation Hospital redevelopment has been completed; if not, when it is expected to be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38032/19]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Health Service Executive recently published its Capital Plan for 2019-2021 outlining 250 projects to be progressed over the three-year period.

The Capital Plan includes the redevelopment of the National Rehabilitation Hospital in Dún Laoghaire, which is currently under construction and is expected to become operational next year.

As the Health Service Executive is responsible for the delivery of public healthcare infrastructure projects, I have asked the HSE to respond to you directly in relation to this matter.

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

138. To ask the Minister for Health if the Cork University Hospital radiation oncology unit has been completed; if not, when it is expected to be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38033/19]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Health Service Executive recently published its Capital Plan for 2019-2021 outlining 250 projects to be progressed over the three-year period.

The Capital Plan includes the new radiation oncology development at Cork University Hospital, which is currently being equipped and commissioned and is expected to become operational by the end of this year.

As the Health Service Executive is responsible for the delivery of public healthcare infrastructure projects, I have asked the HSE to respond to you directly in relation to this matter.

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

139. To ask the Minister for Health if the Waterford University Hospital ward block has been completed; if not, when it is expected to be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38034/19]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Health Service Executive recently published its Capital Plan for 2019-2021 outlining 250 projects to be progressed over the three-year period.

The Capital Plan includes a new ward block development at University Hospital Waterford, which is expected to be completed by the end of this year.

As the Health Service Executive is responsible for the delivery of public healthcare infrastructure projects, I have asked the HSE to respond to you directly in relation to this matter.

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

140. To ask the Minister for Health if phases 2 to 4 of the clinical decision unit (details supplied) at Our Lourdes Hospital, Drogheda has been completed; if not, when it is expected to be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38035/19]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Health Service Executive recently published its Capital Plan for 2019-2021 outlining 250 projects to be progressed over the three-year period.

The Capital Plan includes a number of developments at Our Lady of Lourdes Hospital, Drogheda, which are expected to be completed and become operational by the end of this year.

As the Health Service Executive is responsible for the delivery of public healthcare infrastructure projects, I have asked the HSE to respond to you directly in relation to this matter.

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

141. To ask the Minister for Health if the Letterkenny University Hospital rebuild including radiology has been completed; if not, when it is expected to be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38036/19]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Health Service Executive recently published its Capital Plan for 2019-2021 outlining 250 projects to be progressed over the three-year period.

The Capital Plan includes a number of projects at Letterkenny University Hospital, which are currently under construction, including the replacement radiology department.

As the Health Service Executive is responsible for the delivery of public healthcare infrastructure projects, I have asked the HSE to respond to you directly in relation to this matter.