395. To ask the Minister for Education and Skills the position regarding the construction of a new school (details supplied); if the schedule of accommodation has been completed; and if he will make a statement on the matter. [35809/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The building project for the school referred to by the Deputy is in the process of being devolved to Waterford & Wexford Education and Training Board (WWETB) for delivery.

I can confirm that the schedule of accommodation for the proposed new school has been completed and a copy has been provided to the patron.

The next step in the process is to put in place a Service Level Agreement (SLA) between my Department and WWETB. The Department is currently carrying out the preparatory work necessary to issue the SLA to WWETB for its signature.

Thereafter, the ETB will procure a design team for the project to design the building, obtain the necessary statutory planning permission and move the project onward to construction in due course. As the project is at an early stage in the delivery process, it is not possible at this time to give a date for its completion.

Photo of James BrowneJames Browne (Wexford, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

396. To ask the Minister for Education and Skills the position regarding the construction of a new school (details supplied); and if he will make a statement on the matter. [35810/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The major building project referred to by the Deputy is at an advanced stage of architectural planning, Stage 2(b) – Detailed Design which includes the application for Planning Permission, Fire Cert and Disability Access Cert and the preparation of tender documents.  All statutory approvals have been secured. 

The Design Team is currently completing the Stage 2(b) report for submission to the Department for review.  Upon receipt and review of the Stage 2(b) report the Department will revert to Board of Management with regard to the further progression of the project at that time.