188. To ask the Minister for Finance the capital projects which have been delayed under Project Ireland 2040 under the remit of his Department and agencies in tabular form; when these projects will commence; and if he will make a statement on the matter. [30883/19]
Jack Chambers (Dublin West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
189. To ask the Minister for Finance the capital projects which have commenced under Project Ireland 2040 under the remit of his Department and agencies in tabular form; and if he will make a statement on the matter. [30919/19]
Jack Chambers (Dublin West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
192. To ask the Minister for Finance if expenditure estimates for capital projects under Project Ireland 2040 under the remit of his Department and agencies match projected cost requirements in tabular from; and if he will make a statement on the matter. [30965/19]
Paschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source
I propose to take Questions Nos. 188, 189 and 192 together.
I wish to inform the Deputy that neither my Department nor the 17 bodies under the aegis of my Department currently have any capital projects or expenditures under Project Ireland 2040.
However, one of the bodies under the aegis of my Department, the National Treasury Management Agency, through the National Development Finance Agency (NDFA), is currently advising on a number of projects under Project Ireland 2040 and it should be noted that the NDFA is not the sponsoring or sanctioning authority for these projects.