Written answers

Tuesday, 9 July 2019

Department of Communications, Climate Action and Environment

Broadband Service Provision

Photo of Pearse DohertyPearse Doherty (Donegal, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

577. To ask the Minister for Communications, Climate Action and Environment his plans to extend high speed fibre broadband to a household (details supplied) in County Donegal; and if he will make a statement on the matter. [29330/19]

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Every home, farm, school and business in Ireland will have access to high speed broadband – no matter where they are located – following the Government’s decision to approve the appointment of a preferred bidder to the National Broadband Plan. Under this plan, Ireland will becomes one of the first countries in the world to ensure that those in rural areas have the same digital opportunities as those in urban areas.

The premises referenced by the Deputy is in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map, which is available on my Department's website at .

The AMBER areas represent the target areas for the proposed State led Intervention under the NBP.

This intervention is the subject of the procurement process to engage a company to build, operate and maintain the NBP State intervention network. I recently brought a recommendation to Government to confer Preferred Bidder status on Granahan McCourt, the remaining bidder in the NBP procurement process and Government agreed to this.

The Government Decision of 7 May 2019 means that it is intended to award the State Intervention contract to the Bidder. This award is subject to contract close, including finalisation of financial and legal documents. Deployment of the NBP State Intervention network will commence shortly after that.

The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment.

In the first year of this roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county.

BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations. A deployment plan will be made available by the Bidder once the contract is signed.

The Bidder is aiming to pass 133,000 premises by end of the second year of the overall deployment, with 70-100,000 passed each year thereafter until roll out is completed.