Written answers

Tuesday, 14 May 2019

Department of Education and Skills

Schools Building Projects Status

Photo of Kathleen FunchionKathleen Funchion (Carlow-Kilkenny, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

152. To ask the Minister for Education and Skills the progress in building a new school building for a school (details supplied); and when the pre-qualification of contractors will be finalised and approved. [20442/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the deputy is at an advanced stage of architectural planning, Stage 2b (Detailed Design). The Stage 2(b) submission has been reviewed by my Department and comments have issued to the school and its Design Team.

The Design Team is currently working on a submission to my Department outlining the steps required to achieve compliance with Part L of the Building Regulations 2017 (NZEB "Near Zero Energy Building"). This is a new requirement arising from the introduction of Part L (Conservation of Fuel and Energy) of the Building Regulations to ensure compliance with the EU Energy Performance of Buildings Directive (EPBD).

When the NZEB submission has been received, my Department at that point will consider authorising this project to commence the pre-qualification process to create a shortlist of contractors to which the project will be tendered.

Pre-qualification normally takes between 8 and 12 weeks to complete.

Comments

No comments

Log in or join to post a public comment.