Road Projects Data

Photo of Noel GrealishNoel Grealish (Galway West, Independent)
Link to this: Individually | In context | Oireachtas source

204. To ask the Minister for Transport, Tourism and Sport the final cost of the abandoned Galway city outer bypass project by category of expense such as planning and design, legal costs, environmental impact studies and so on; the estimated cost of the project when it was originally commenced; the original estimated timeframe for completion of the project; the length of time that elapsed from when the road was initially announced until it was formally abandoned; and if he will make a statement on the matter. [8562/19]

Photo of Shane RossShane Ross (Dublin Rathdown, Independent)
Link to this: Individually | In context | Oireachtas source

As Minister for Transport, Tourism & Sport, I have responsibility for overall policy and funding in relation to the national roads programme. Under the Roads Acts 1993-2015, the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII) in conjunction with the local authorities concerned.

Noting the above position, I have referred the question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.