Written answers

Thursday, 14 February 2019

Department of Education and Skills

Capital Expenditure Programme

Photo of Jonathan O'BrienJonathan O'Brien (Cork North Central, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

105. To ask the Minister for Education and Skills the capital projects completed by his Department since 2011; the initial contract value of same; the final cost of same; and the final cost of the capital projects that have had an ex post review in tabular form. [7848/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

School building projects in excess of €10m typically arise at post-primary level rather than at primary level.

Building Contracts in excess of €10m

NumbersCountyRoll No.School YearContract Sum Incl VATDate LOA signed/

Contract commenced
Final Account Agreed Sum incl VATReason for variation: Change Orders, Conciliation etc
1Cork68264REdmund Rice College, Carrigaline2017€13,322,007.8424/03/2016€14,683,207.60Approved change orders
2Dublin60029JClonkeen College, Dublin201711,303,02022/06/201511,615,716.32Approved Change Order
3Limerick20175ALimerick ETNS (Linked with 20181S)2017€12,451,133.7630/08/2016€12,668,568.52Approved change orders
Limerick20181SGS an Raithin (Linked with 20175A)2017
4Dublin68082LColáiste Ghlór na Mara, Balbriggan2016€14,364,344.2806/11/201514,911,274.40Approved change orders
5Meath76196WAshbourne Post-Primary School, Ashbourne - linked to 20382F and 20396Q2016€17,308,750.0010/09/2015€18,303,847.37Approved change orders
Meath20382FGaelscoil Na Mí, Ashbourne - linked to 76196W & 20396QO2016
Meath20396Q Ashbourne Educate Together National School, linked to 76196W & 20382F2016
6Cork62640MSt Angela's College, Cork201511,423,467.5010/03/201413,039,322.04Approved Change Order and Conciliation Award
7Dublin76129HArdgillan Community College, Balbriggan201512,319,627.5101/07/201313,194,070.88Approved Change Orders
8Dublin76152CClonburris Post-Primary School, Clonburris, Lucan2015€12,892,172.1127/03/2014€15,761,147.55Approved change orders and conciliation

9Galway71330VColáiste na Coiribe, Bóthar Thuama2015€10,830,109.0021/7/2014€11,524,790Approved change orders
10Dublin81001LNewpark Comp, Blackrock201412,468,451.0309/07/201312,733,512.97Approved Change orders
11Meath76173KColáiste na Mí, Navan (linked to 20179I)2014€11,379,235.4220/12/201211,668,067.63Approved change orders
Meath20179ISt Stephen's NS, Navan (linked to 76173K)2014
12Meath18762DSN Realt na Mara (Girls) Mornington (joint project with 18767M)2014€10,101,818.4904/01/2013€10,354,045Approved change orders
Meath18767MSN Realt na Mara (Boys) Mornington (joint project with 18762D)2014
13Dublin 76130PLuttrellstown Community College 2013€13,046,425.0001/08/2012€13,369,738.02Approved change orders
14Monaghan76091IGaelcholáiste Oiriall (Linked to 76095Q & 19936P)2013€30,770,156.5315/08/2011€31,643,045.78Approved change orders
Monaghan76095QMonaghan Institute of Further Education (Linked to 76091I & 19936P2013
Monaghan19936PGaelscoil Ultain (Linked to 76095Q & 76091I)2013
15Dublin76098WPobail Scoil Setanta, Phibblestown - linked to 20247W2011€19,921,240.7716/12/2008€20,292,897.58Approved change orders
Dublin 20247WScoil Grainne, Phibblestown - linked to 76098W2011

It can generally take quite a while for final accounts on projects to be submitted by contractors and then get finalised and agreed. The attached table sets out the position in respect of large-scale school building projects in excess of €10m where the final account has been agreed. In summary, it shows that there was just over a 5% difference between the tender (contract) sum and the agreed final account for large-scale school building projects delivered since 2011. There is a process in place for dealing with requests for change orders to existing contracts and these typically relate to matters such as unforeseen events during the construction process, requirement for additional works etc.

My Department carefully manages and control costs on all projects in order to ensure best possible outcomes for the investment being made under the capital programme.

The measures in place to manage and control costs on large-scale school building projects include:

- Detailed procedures in place for appraisal, design, tender and construction of large-scale school building projects.

- Standardisation of sizes and layouts for classrooms and other rooms in schools.

- Detailed design team procedures that involve Department approval for progression through the various stages of design and tendering.

- NDesign Team fees tendered on percentage basis and then locked in to a fixed sum when design has been developed at Stage 2A of design process.

- Planning permission and design completed before tender process commences which gives clarity to tenderers on scope of project

- Contracts tendered on a fixed price basis using the standard form of Government contract – which gives certainty in relation to managing the impact of construction inflation.

- Procedures in place for provision of monthly progress reports and arrangements for dealing with any requests for change orders to existing contracts.

In addition to the school projects listed in the attachment 20 schools were delivered during the period by way of Public Private Partnership (PPP). In the case of such projects, the cost (which also includes Facilities Management and lifecycle costs) is determined at Financial Close and payment by the Department is by way of monthly Unitary Charges over the operational period, usually 25 years.

Information in respect of capital projects in the Higher Education Sector with building contracts in excess of €10m and with final accounts agreed will be forwarded separately to the Deputy when the relevant information is collated and finalised.