Written answers

Tuesday, 12 February 2019

Department of Transport, Tourism and Sport

Road Projects Expenditure

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

622. To ask the Minister for Transport, Tourism and Sport the breakdown of the €200 million allocation in 2019 for the N22 Ballyvourney to Macroom route; the date in 2019 building will commence; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6884/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

624. To ask the Minister for Transport, Tourism and Sport the breakdown of the €115 million allocation in 2019 for the Dunkettle interchange; the date in 2019 construction will commence; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6886/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

625. To ask the Minister for Transport, Tourism and Sport the breakdown of the €100 million allocation in 2019 for the N25 Dungloe to Glenties road; the date in 2019 the project will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6887/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

627. To ask the Minister for Transport, Tourism and Sport the breakdown of the €39 million allocation in 2019 for the N56 Mountcharles to Inver Road route; the date in 2019 the project will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6889/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

629. To ask the Minister for Transport, Tourism and Sport the breakdown of the €42 million allocation in 2019 for the Listowel bypass; the date in 2019 it will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6891/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

636. To ask the Minister for Transport, Tourism and Sport the breakdown of the €592 million allocation in 2019 for the M11 Gorey to Enniscorthy motorway; the date in 2019 the project will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6898/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

637. To ask the Minister for Transport, Tourism and Sport the breakdown of the €385 million allocation in 2019 for the N25 New Ross bypass; the date in 2019 the project will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6899/19]

Photo of Shane RossShane Ross (Dublin Rathdown, Independent)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 622, 624, 625, 627, 629, 636 and 637 together.

The Government is committed to delivering Project Ireland 2040 within the overall multi-year resource envelope that has been set out. For 2019, the capital allocation has increased by €1,325 million or just over 22% above the 2018 allocation as stated in the Revised Estimates for Public Services 2019.

With regard to implications arising from the National Children’s Hospital project, the Government is currently considering how the additional cost pressures will be accommodated within the multi-year envelope, with a minimum of disruption to the planned rollout and delivery of important infrastructure projects under Project Ireland 2040.

As Minister for Transport, Tourism & Sport, I have responsibility for overall policy and funding in relation to the national roads programme. Under the Roads Acts 1993-2015, the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII) in conjunction with the local authorities concerned.

At this time, there are no implications for the allocation for this project or programme from the financing of the National Children’s Hospital.

Noting the above position, I have referred the question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

626. To ask the Minister for Transport, Tourism and Sport the breakdown of the €52 million allocation in 2019 for the Coonagh to Knockalisheen route; the date in 2019 the project will commence; if it will be impacted by the cost overrun with the national children's hospital; and if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6888/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

630. To ask the Minister for Transport, Tourism and Sport the breakdown of the €18 million allocation in 2019 for a facility (details supplied); the date in 2019 it will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6892/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

632. To ask the Minister for Transport, Tourism and Sport the breakdown of the €7 million allocation in 2019 for the Portlaoise southern distributor road; the date in 2019 the project will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6894/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

633. To ask the Minister for Transport, Tourism and Sport the breakdown of the €5 million allocation in 2019 for the Laytown to Bettystown link road; the date in 2019 the project will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6895/19]

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

634. To ask the Minister for Transport, Tourism and Sport the breakdown of the €4 million allocation in 2019 for the Dingle relief road; the date in 2019 the project will be completed; if it will be impacted by the cost overrun with the national children's hospital; if he or his officials have been consulted by the Department of Public Expenditure and Reform in this regard; and if he will make a statement on the matter. [6896/19]

Photo of Shane RossShane Ross (Dublin Rathdown, Independent)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 626, 630 and 632 to 634, inclusive, together.

The Government is committed to delivering Project Ireland 2040 within the overall multi-year resource envelope that has been set out. For 2019, the capital allocation has increased by €1,325 million or just over 22% above the 2018 allocation as stated in the Revised Estimates for Public Services 2019. With regard to implications arising from the National Children’s Hospital project, the Government is currently considering how the additional cost pressures will be accommodated within the multi-year envelope, with a minimum of disruption to the planned rollout and delivery of important infrastructure projects under Project Ireland 2040.

The improvement and maintenance of regional and local roads is the statutory responsibility of each local authority, in accordance with the provisions of Section 13 of the Roads Act 1993. Works on those roads are funded from the Council's own resources supplemented by State road grants.

Each local authority is the contracting authority for the purpose of implementation of the regional and local road improvement projects included in Project Ireland 2040 and is responsible for the project schedule.

The figures mentioned in the Deputy's Parliamentary Questions are the total estimated cost of each project. As regards grant expenditure to date and 2019 allocations, the Regional and Local Road allocation and payment booklets available in the Oireachtas library provide details of grant payments and allocations. The Capital Tracker published by the Department of Public Expenditure and Reform provides information on the status of the projects. The relevant link is:

At this time, there are no implications for the allocation for this project or programme from the financing of the National Children’s Hospital.