Written answers

Thursday, 7 February 2019

Department of Public Expenditure and Reform

Flood Relief Schemes Status

Photo of James BrowneJames Browne (Wexford, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

38. To ask the Minister for Public Expenditure and Reform his plans for flood relief schemes in County Wexford; and if he will make a statement on the matter. [5760/19]

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As the Deputy is aware, the River Slaney (Enniscorthy) Flood Relief Scheme is at an advanced stage of planning and design, and it is hoped to proceed to formal Exhibition as required under the Arterial Drainage Acts (ADA) in late March/early April this year, following which, if the scheme proposals are generally well received, the design will be finalised and all required documentation will be submitted to the Minister for Public Expenditure and Reform, requesting formal confirmation of the scheme under the ADA. It is hoped therefore that the tender process for contractors to construct the scheme will begin in June 2019, and if all goes well, it is hoped to commence construction in late 2019/early 2020.

Works are also ongoing and/or planned in a number of other areas in County Wexford –

Wexford Town

The Flood Risk Management Plan for the South East River Basin District includes proposed structural flood relief measures for Wexford town. These will consist of building hard defences and improvement of channel conveyance. These measures for Wexford were included in the initial tranche of investment which I announced on 3rd May 2018 with €257m funding for 50 new projects to proceed to detailed project level design and construction. Work on the Wexford project has commenced with Wexford County Council (WCC) leading on its implementation and a Project Steering Group has been established.

New Ross

Flood defence works have been carried out by contractors on behalf of WCC and some funding for these works has been provided by the Office of Public Works (OPW). Additional works in the area require to be carried out by WCC to ensure protection to the 1 in 200 year standard, and funding for this will be provided by the OPW.

Rosslare

The flood and erosion risk in the Rosslare area north of the seaport and the options for mitigating that risk are under consideration by WCC. A meeting was held between WCC and its consultants RPS and the OPW in December 2018 in this regard.

Photo of Aindrias MoynihanAindrias Moynihan (Cork North West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

39. To ask the Minister for Public Expenditure and Reform the status of the outline design stage for the construction of the flood relief works on the Sullane River at Ballyvourney, County Cork; if the preferred options for the scheme are finalised; and if he will make a statement on the matter. [5958/19]

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am advised by the Commissioners of Public Works that the Baile Mhúirne and Ballymakeera Flood Relief scheme is currently at outline design stage, and the preferred options for the scheme are in the process of being finalised.

The River Sullane has a history of freshwater pearl mussels, which have protected status as an Annex II listed species under the EU Habitats Directive. An environmental survey was carried out to establish the status of the population and the likely impact of any works.

Given the impact the proposed works could have on the Fresh Water Pearl Mussel population, a proposal to translocate Fresh Water Pearl Mussel from the River Sullane and reintroduce them post works was submitted to, and has now been approved by, the NPWS and the Department of Culture, Heritage and the Gaeltacht, allowing the scheme preparations to progress to site investigation, which will inform the preferred options for the scheme. A site investigation was completed in Q3 2018 and the results will further assist in determining the preferred options, and in refining construction cost estimates.

The emerging preferred option was presented to members of the public and relevant stakeholders at a second Public Information Day in March 2018. A public exhibition of the preferred scheme is expected to take place in Spring 2019.

When these stages are successfully completed and, subject to the proposals being accepted by the public and the stakeholders, and the scheme being technically, environmentally and economically viable, the scheme will then proceed to formal Confirmation by the Minister for Public Expenditure and Reform under the Arterial Drainage Acts 1945 and 1995, and then move onto detailed design stage, following which the scheme can progress to construction stage.

In the interim, the OPW has approved funding of €187,248 for temporary flood defence works in Ballymakeera under its Minor Flood Mitigation Works & Coastal Protection Scheme. In addition, OPW environmental consultants (RPS) for the Scheme have prepared a Preliminary Invasive Alien Species Management Plan (IASMP) for the OPW in response to the findings of ecological survey work undertaken during 2017 and 2018. This plan identifies the presence and location of invasive species around or close to the works area of the FRS. These include Giant Knotweed, Japanese Knotweed and Himalayan Knotweed.

The preliminary IASMP has been prepared in order to commence treatment of Invasive Species in the immediate vicinity of the proposed scheme works area in advance of interim and main scheme works and has been provided to Cork County Council, who have agreed to undertake treatment of invasive species for the Scheme on behalf of the OPW.

The optimal time to begin treatment of knotweed will be late summer / early autumn 2019.

My Office continues to liaise with Cork County Council and local representatives on this Scheme.

Comments

No comments

Log in or join to post a public comment.