Written answers
Tuesday, 29 January 2019
Department of Health
National Children's Hospital
Brendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
431. To ask the Minister for Health if projects in an area (details supplied) will be delayed or deferred due to overruns on the capital budget of the national children's hospital; and if he will make a statement on the matter. [4311/19]
Simon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The Health Service Executive is currently developing its Capital Plan for 2019. The HSE Capital Plan will determine the projects that can progress in 2019 having regard to the available capital funding, the number of large national capital projects currently underway and the relevant priority of each project. The requirements of the new children's hospital and other health capital projects, currently at various stages of development, are being considered as part of this process.
Mattie McGrath (Tipperary, Independent)
Link to this: Individually | In context | Oireachtas source
432. To ask the Minister for Health further to Parliamentary Question No. 163 of 23 January 2019, the reason the definitive business case cannot be immediately released as per the process outlined in his reply to Parliamentary Question No. 552 of 4 April 2017; and if he will make a statement on the matter. [4312/19]
Simon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source
As per Parliamentary Question No. 163 of 23 January 2019, the National Paediatric Hospital Development Board produced the final project brief and definitive business case and I have asked the National Paediatric Hospital Development Board to respond to your request directly, as soon as possible.