379. To ask the Minister for Education and Skills the status of developments at a school (details supplied); and if he will make a statement on the matter. [1593/19]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The major building project referred to by the Deputy is currently at an advanced stage of architectural planning, Stage 2(b) – Detailed Design.
The pre-qualification process to select a shortlist of suitable contractors is now complete and the Design Team has also completed the necessary work to ensure the new school building is NZEB compliant.
The project is currently being progressed to tender stage.
A tender stage normally takes between 7 and 8 months to complete.