Flood Relief Schemes

Photo of Michael McGrathMichael McGrath (Cork South Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

182. To ask the Minister for Public Expenditure and Reform further to Parliamentary Question No. 89 of 26 April 2018, if he will provide a detailed update on plans for a flood relief scheme (details supplied) in County Cork; the funding committed; the steps in the process; the timeline for the completion of the project; and if he will make a statement on the matter. [49434/18]

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

A pre-feasibility study into the flooding issues in Ballinhassig has been completed by the Office of Public Works (OPW) and has identified a preferred option for the area. Further assessment of the environmental impacts are currently being progressed to inform the planning process, after which the project will progress to planning and detailed design. It is not possible to provide a timeframe for the project at this time but provision has been made in OPW’s multi annual financial profiles for the progression of the scheme to implementation.

Comments

No comments

Log in or join to post a public comment.