Written answers

Wednesday, 24 October 2018

Department of Public Expenditure and Reform

Office of Public Works Projects

Photo of Clare DalyClare Daly (Dublin Fingal, Independent)
Link to this: Individually | In context | Oireachtas source

136. To ask the Minister for Public Expenditure and Reform further to Parliamentary Question No. 86 of 17 October 2018, if he will quantify the relatively small number of projects the 4500,000 limit has been exceeded. [44085/18]

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Measured Term Maintenance Contract which expired on 12thOctober 2018 set a single order limit at €500,000 exclusive of VAT.

During this contract i.e. from 13thOctober 2014 to 12thOctober 2018 the number of projects that have exeeeded the contract limit of €500,000 exclusive of VAT were as follows:

Projects, that have exceeded €500k exclusive of VAT and that commenced between 13/10/2014 and 12/10/2018Number of Projects
2014 0
2015 3
2016 2
2017 0
2018 7