Schools Building Projects Data
Mick Wallace (Wexford, Independent)
Link to this: Individually | In context | Oireachtas source
61. To ask the Minister for Education and Skills the number of school building projects that have been affected by building contractors running into financial difficulties since January 2018; the names of the schools in each case; and if he will make a statement on the matter. [42114/18]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Since the beginning of 2018, 18 school building projects have been affected in respect of two contractors who have encountered financial difficulties. A list of the 18 schools in question is as follows:
County | School | Roll Number |
---|---|---|
Cork | St Colman’s College, Midleton | 71050P |
Cork | Colaiste an Chraoibhin, Fermoy | 70990M |
Kildare | Maynooth Post-Primary School | 70700A |
Kildare | Maynooth Community College | 76193Q |
Louth | Scoil Ui Mhuiri, Dunleer | 71780G |
Carlow | Tyndall College | 70420R |
Carlow | Carlow Institute of Further Education | 76514K |
Meath | Eureka Secondary School, Kells | 64410F |
Wicklow | Colaiste Raithin, Bray | 70821M |
Wicklow | Ravenswell Primary School, Bray | 07246U |
Wexford | Loreto Secondary School | 63660A |
Dublin | Gaelscoil Bhaile Munna | 20015B |
Dublin | Gaelscoil Bharra, Cabra | 20047O |
Laois | Portlaoise Amalgamation | 20270R & 20480F |
Offaly | Tullamore College | 72560C |
Wicklow | Arklow Community College | 70740M |
Wexford | New Ross Jnr & Snr Schools | 20481H & 20482J |
Louth | Scoil Padraig Naofa, Drogheda | 17949O |
One of the building contractors in question went into Liquidation; this contractor was involved in 15 of the projects. The other contractor, who was engaged in the other three projects affected, underwent a Company Voluntary Arrangement (CVA) process, which is similar to Examinership.
Of the 18 projects - 8 of the schools are now occupied, 1 is due to be completed by late October/early November 2018, a further 4 schools are due to be completed in late 2018/2019 and 5 of the projects are currently being retendered.
On a small number of projects where the schools are occupied but some site works have yet to be completed, the Design Teams are currently in negotiation with the respective Bondsman with a view to having the works completed as soon as possible.
I would like to assure the Deputy that my Department is committed to achieving the earliest possible completion dates for all the projects concerned.