Written answers
Tuesday, 16 October 2018
Department of Education and Skills
Schools Building Projects Status
Bernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source
258. To ask the Minister for Education and Skills the extent to which the various schools affected by a contractor (details supplied) are progressing towards completion and available for the intake of pupils and students; and if he will make a statement on the matter. [42490/18]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The following table sets out the current position in relation to the schools affected by the collapse of the building contractor referred to by the Deputy.
County | Roll No. | School | Type of project | Original planned Completion date | Revised planned Completion date |
---|---|---|---|---|---|
Dublin City | 20047O | Gaelscoil Bharra, Cabra | New 8 classroom school | 07/09/2017 | School ready for occupation on 1/9/17, some ground works still to be completed |
Laois | 20270R | Portlaoise amalgamation, (St Paul's, Sacred Heart & Scoil Mhuire) Portlaoise Rd, Portlaoise, Co. Laois. | New Schools - 3 existing schools amalgamating into 2 new schools - Two new 24 classroom schools with a combined GP Hall. | 12/04/2016 | Jnr School ready for occupation on 9/6/17 - Snr School ready for occupation on 29/8/17, some ground works still to be completed |
Offaly | 72560C | Tullamore College | Demolition of the existing single storey secondary school buildings and their replacement with a 7,076m2 part single part two storey school building to provide accommodation for 675 pupils | 29/06/2016 | School ready for occupation on 27/2/17, some ground works still to be completed |
Wexford | 12372G | New Ross Jnr & Snr Schools, Castlemoyle | 2 new 18 classroom schools each with a 2 classroom ASD Unit | 15/06/2016 | Schools ready for occupation on 25/01/17, some snags/defects still to be rectified |
Wicklow | 70740M | Arklow Community College, Coolgreaney Rd, Arklow, Co. Wicklow. | New school to cater for 710 pupils | 17/06/2016 | School ready for occupation on 23/12/15, some ground works still to be completed |
Cork | 71050P | St Colman's College, Midleton, Co Cork | Extension of 5,640sqm including ASD Unit PE Hall to provide accommodation for 1000 pupils | 10/02/2017 | School should be ready for occupation Sept 2019 |
Cork | 70990M | Coláiste an Chraoibhin, Fermoy, CO Cork | Extension of 3,845 sqm including ASD Unit PE Hall to provide accommodation for 850 pupils | 15/12/2016 | School should be ready for occupation Sept 2019 |
Kildare | 70700A | Maynooth Post Primary School, Maynooth | Replacement school for 1000 pupils | 18/05/2019 | School should be ready for occupation June 2020 |
Kildare | 76193Q | Maynooth Community College, Maynooth | New 1000 pupil with a shared Sports Hall with Maynooth Post Primary School | 18/05/2019 | School should be ready for occupation June 2020 |
Carlow | 70420R | Tyndall College | 1000 pupil school | Q1/2018 | School should be ready for occupation by end of 2018/early 2019. |
Carlow | 76514K | Carlow Institute of Further Education | 1000 pupil school | Q1/2018 | School should be ready for occupation by end of 2018/early 2019. |
Meath | 64410F | Eureka Secondary School, Kells | 800 pupil school | Q1/2018 | School should be ready for occupation by end of 2018/early 2019. |
Wicklow | 70821M | Coláiste Raithin, Bray | 450 pupil school | Q4/2017 | School ready for occupation on 31/08/2018 |
Wicklow | 07246U | Ravenswell Primary School, Bray | 24 Classroom School | Q4/2017 | School ready for occupation on 18/09/2018 |
Wexford | 63660A | Loreto Secondary School | 900 pupil school | Q4/2017 | School ready for occupation on 23/08/ 2018 |
Bernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source
259. To ask the Minister for Education and Skills the position in regard to the development of a school (details supplied); if the plans have advanced sufficiently to ensure the availability of the facility as and when required; and if he will make a statement on the matter. [42491/18]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The project to which the Deputy refers has been devolved for delivery to the local Education and Training Board (ETB).
The project is at stage 2b of the architectural planning process. When stage 2 b has been approved, the next stage is tendering for a contractor. My Department expects to be able to approve the project to move to the tender stage shortly.
My Department will meet the interim accommodation needs of the school pending the delivery of its new building.