126. To ask the Taoiseach the cost of each seminar held on Project Ireland 2040 up to and including September 2018 by his Department. [39590/18]

Photo of Leo VaradkarLeo Varadkar (Dublin West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

My Department led on the launch of Project Ireland 2040 in Sligo and the four subsequent regional events in Galway, Limerick, Cork and Waterford.

A breakdown of costs associated with each of the regional events can be found in the table.

A number of strand launches were held in the first half of 2018; these were led and funded by the relevant line Department.

The responsibility for the communication of Project Ireland 2040 has now transitioned to the Project Ireland 2040 Delivery Board – led by the Department of Public Expenditure and Reform and the Department of Housing, Planning and Local Government.

EventCostCosts incurred includes
Sligo launch (Feb 16th)€6,430.99Attendance of Cabinet Secretariat/Protocol staff to support the Cabinet meeting

Attendance of staff to support the launch

Attendance of Officials/advisers with policy responsibility

Attendance of Press Officers to support media engagements
Waterford and Cork regional events (March 8th/9th)€4,490.86Attendance of Protocol staff

Attendance of staff to support the event

Attendance of Press Officers to support media engagements

Catering costs
Galway and Limerick regional events (April 16th/17th)€4,491.78Attendance of Protocol staff

Attendance of staff to support the event

Attendance of Press Officers to support media engagements

Catering costs

Please note that costs listed above are reflective of costs paid by my Department to date. There are costs yet to be invoiced.