Written answers
Tuesday, 18 September 2018
Department of Public Expenditure and Reform
Office of Public Works Projects
Joan Burton (Dublin West, Labour)
Link to this: Individually | In context | Oireachtas source
148. To ask the Minister for Public Expenditure and Reform when the OPW will appoint engineering consultants for the planned State data centre at Backweston, Celbridge, County Kildare; when planning permission will be sought for the project; when construction on the project will commence; and if he will make a statement on the matter. [37808/18]
Paschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Engineering consultant tenders were received on 10 September 2018. They are presently being assessed. Planning application is due to be lodged in Quarter 4 2018. Construction tender documents will be issued in Q 2 2019. On-site work should commence in Quarter 4 2019.