Written answers

Friday, 7 September 2018

Department of Communications, Climate Action and Environment

North-South Interconnector

Photo of Niamh SmythNiamh Smyth (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

1055. To ask the Minister for Communications, Climate Action and Environment the reason he is delaying publishing the studies in relation to the North-South interconnector; the timeframe for publication; and if he will make a statement on the matter. [36658/18]

Photo of Denis NaughtenDenis Naughten (Roscommon-Galway, Independent)
Link to this: Individually | In context | Oireachtas source

In 2017 I commissioned two studies designed to address the main points of the motions passed in Dáil and Seanad Éireann as well as key concerns expressed by the parties opposed to the development of the North South Interconnector as an overhead line. The first is an independent study to examine the technical feasibility and cost of undergrounding the interconnector. The second study is focused on the levels of compensation provided to land and property owners in proximity to high-voltage transmission lines in a European context.​ Both studies are now completed and have been submitted to me. I expect to bring both reports to Government in the coming weeks and will publish them as soon as possible thereafter.

Comments

No comments

Log in or join to post a public comment.