Department of Employment Affairs and Social Protection

Departmental Expenditure

Photo of Barry CowenBarry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

550. To ask the Minister for Employment Affairs and Social Protection the specific reason for the underspend in gross voted expenditure of €2 million as outlined in Appendix V of the June 2018 Fiscal Monitor; the specific projects that have an underspend; the value of the underspend on each project; and if she will make a statement on the matter. [31306/18]

Photo of Regina DohertyRegina Doherty (Meath East, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Department of Employment Affairs and Social Protection has a capital budget of €11m in 2018 (including €1m carryover from 2017).

The projected capital underspend outlined in Appendix V of the June 2018 Fiscal Monitor relates to the A.2.(v) Office Equipment and External IT Services and A.2.(vi) Office Premises Expenses Subheads. However, the actual capital underspend at end June was €2.29m (excluding capital carry over).

Table 1 provides details of the current underspend.

Table 1

ProjectEnd June UnderspendReason for Underspend
A.2.v Office Equipment and External IT Services:
Ongoing purchase of computer hardware, photocopiers, other non-IT office machinery, software licenses including storage technology, investment in server infrastructure and in virtualisation technology etc.€0.83mThe timing of this expenditure can be difficult to profile on a monthly basis. It is anticipated that these monies will be expended over the course of the year.
Intreo Centre Online Self Service€0.2mProject underway but expenditure will be not be incurred until Q3 and Q4.
A.2.v Office Premises Expenses
Tuam€0.8mThe reasons relate primarily to delays in the planning and contracting process.
Longford€0.1mThe reasons relate primarily to delays in the planning and contracting process.
Dungarvan€0.14mThe reasons relate primarily to delays in the planning and contracting process.
Nenagh€0.22mThe reasons relate primarily to delays in the planning and contracting process.